Make an opening of Ø 155 mm for the roof duct.
•
Connect the pipes vertically to the mouth of the appliance. Push them firmly together and place the clip
bindings.
•
Determine the length of the pipes needed and make sure that the transfer tile or the universal roof tile is
well fitted to the roof.
•
Saw the outer pipe off to measure, and connect the concentric pipes to the roof duct.
First install the flue system, and then place the gas unit
You may also fit the concentric pipe system before placing the gas unit, but then you must the connection to
the gas unit with a pipe that can be shifted.
Removing the glass
•
Remove the decorative frame by unscrewing the 4 screws
on the left and right side as shown on the drawing.
•
Remove the glass frames by unscrewing the 4 screws as
shown on the drawing.
•
Loosen the screws from the bottom glass frame, these do
not need to be removed.
•
Carefully lift the glass from its place.
Placing a pipe closer
Depending on the total length of the concentric flue system
(100/150 mm) and the choice of outlet it’s possible a pipe
closer needs to placed. The diameter of these pipe closers are
Ø50 mm. Following the instructions below the closer can be
placed in the flue collar inside the combustion chamber as
shown on the illustration.
The standard outlet width is 100 mm
Make sure the pipe closer is installed correctly. Installation in the wrong situations, or the in the wrong
way may cause malfunctioning of the appliance.
!