background image

Winding systems

Page 8 | 10

2007644 [Rev. 4 - en]/2016-03-22

5

6

7

8

(

see Chapter 4/Page

8

)

Dismantling

1

2

3

1

2

4

Winding systems

> 1500

> 1500

The loop of the lifting cord must be fixed to the wall at least

1500 mm above the floor.

Installation procedure

Transfer the fixing points

of the cord winders to

the mounting substruc-

ture.

Attach the cord winders

to the mounting sub-

structure.
Push the cover caps into

the cord winders.

Procedure for securing the pull cord

Wind all of the pull cord

around the two halves of

the cord winder.

Summary of Contents for FS

Page 1: ...d blind with cord operation Type FS S1 S2 XR1 Instructions for installation use and maintenance To be handed over to the operator Please keep for future use Valid from 22 March 2016 Document number 2007644 Rev 4 en ...

Page 2: ... 1 3 Basic safety instructions 3 2 Installation FS S1 S2 XR1 without cable guidance 4 2 1 Overview 4 2 2 Rabbet installation 4 2 3 Angle bracket installation 5 3 Installation of FS with cable guidance 6 3 1 Rabbet installation 6 3 2 Angle bracket installation 7 4 Winding systems 8 5 Operation with lifting cord 9 5 1 9 6 Maintenance 10 6 1 Cleaning 10 6 2 Warranty 10 6 3 Spare parts repairs 10 ...

Page 3: ...These instructions contain important information on the handling installation commissioning operation care and maintenance of this item Other versions or special solutions are not dealt with Permissible activities Performing tasks on the product that are not described in these instructions is not permissible No other alterations additions conversions or maintenance work is to be carried out on the...

Page 4: ...07644 Rev 4 en 2016 03 22 2 Installation FS S1 S2 XR1 without cable guidance 2 1 Overview Type FS Type S1 S2 Type XR1 35 90 35 90 35 35 90 35 35 2 2 Rabbet installation Measuring and drilling the fixing points 15 mm 3 mm 3 mm 3 mm 15 mm 17 mm 3 mm 3 mm 3 mm 17 mm ...

Page 5: ...idance 2007644 Rev 4 en 2016 03 22 Page 5 10 Installing the pleated blind 1 2 3 4 see Chapter 4 Page 8 Dismantling 1 2 3 Angle bracket installation Measuring and drilling the fixing points x x 2 mm x x 2 mm Installing the pleated blind 1 2 3 4 ...

Page 6: ...6 03 22 5 6 see Chapter 4 Page 8 Dismantling 1 3 Installation of FS with cable guidance 3 1 Rabbet installation Measuring and drilling the fixing points 15 mm 3 mm 3 mm 3 mm 15 mm 15 mm 15 mm 17 mm 3 mm 3 mm 3 mm 17 mm 15 mm 17 mm Installing the pleated blind 1 2 3 1 2 4 ...

Page 7: ...ble guidance 2007644 Rev 4 en 2016 03 22 Page 7 10 5 6 see Chapter 4 Page 8 Dismantling 1 2 3 1 2 3 2 Angle bracket installation Measuring and drilling the fixing points x x 2 mm x x 2 mm Installing the pleated blind 1 2 3 4 1 2 ...

Page 8: ...rd must be fixed to the wall at least 1500 mm above the floor Installation procedure Transfer the fixing points of the cord winders to the mounting substruc ture Attach the cord winders to the mounting sub structure Push the cover caps into the cord winders Procedure for securing the pull cord Wind all of the pull cord around the two halves of the cord winder ...

Page 9: ... reach of young children Cords may become wrapped around the neck of a child Move beds cots and furniture away from the cords of window coverings Do not tie cords together Make sure cords do not twist and create a loop 1 2 3 4 5 6 Raise and lower the pleated blind by pulling the lifting cord Wind all of the lift ing cord around the two halves of the cord winder Assembling the safety cord tassel Ca...

Page 10: ...ber of factors that vary from case to case Always follow the manufacturer instructions when using chemical cleaning products In the interest of the environment it is recommended that you only use 100 biologically degradable cleaning products NOTICE Product damage from incorrect cleaning Incorrect cleaning procedures may result in damage to the product or product parts and the surfaces and structur...