Sensor Splitter
6 Commissioning
The WAREMA climatronic®/Wisotronic networks are commissioned separate-
ly one after the other. The networks can be commissioned as usual, either
with the appropriate wizard or manually.
When commissioning the WAREMA climatronic
®
, a small amount of rewiring
work is required.
CAUTION
Only make changes to the bus wiring while the components and networks
are in a de-energised state.
6.1 Procedure for
Wisotronic
Proceed as follows to commission the entire installation.
When switching on the power supply, it is important that you adhere to the
described sequence, or else it will not be possible to commission the unit
properly.
Check that all bus lines are correctly wired (
see Chapter 5.1 on page 18
).
Check that all encoding switches have been correctly set on the sensor split-
ters (only one master, Wisotronic device type, ...).
First switch on the power supply for the weather station and the sensor split-
ter MASTER.
Now switch on the power supply for the Wisotronic devices.
NTTE
The power supply can also be switched on simultaneously for the entire unit.
If the power supply of the weather station and sensor splitter MASTER is
switched on later, it will not be possible to correctly commission the unit.
Now commission the Wisotronic device. Follow the instructions accompany-
ing the Wisotronic.
This completes the commissioning process.