Start-up procedure 

• 

Fill the mineral tank with water: 

Press and hold the extra cycle button for 5 seconds. 

Display will indicate step 1, which is the backwash cycle (as shown above). Once the 
display indicates step 1, slowly open bypass valve and let water run to the drain for    
approximately 5 minutes. This will bleed any air from the system and flush it to the 
drain. After approximately 5 minutes, manually index the valve through the remaining 
cycles as follows: 

• 

Push the extra cycle button 

once to advance the valve to regen step 2 

• 

Push the extra cycle button 

once to advance the valve to regen step 3 

• 

Push the extra cycle button 

once to advance the valve to regen step 4 

 
At regen step 4, allow the control to automatically complete step 4  (brine refill) and return 
to service. This will place the correct amount of water in the brine tank for start-up.  
 
The unit is now pressurized with water and ready for service

Proceed to setting current 

time. 

 

Placing unit into service 

Summary of Contents for BrassMaster plus+

Page 1: ...Metered Water Softener Installation Operation manual Manufactured by Water Control Corporation 7150 143rd Ave NW Ramsey MN 55303 Tel 763 427 9635 Fax 763 427 5665...

Page 2: ...rn into the female threaded opening on the back side of the control valve Connect 5 8 drain line supplied in parts bag to barbed end of drain line fitting and run to a nearby drain Be sure not to subm...

Page 3: ...5 minutes manually index the valve through the remaining cycles as follows Push the extra cycle button once to advance the valve to regen step 2 Push the extra cycle button once to advance the valve t...

Page 4: ...between regen eration cycles System will regenerate regardless of usage if the days since last regeneration cycle equals the day override setting This insures regular regeneration periods In areas of...

Page 5: ...tized and ready for operation 3 Adjust Regeneration Time Press the Extra Cycle button This setting determines the time of day that the unit will enter the regeneration cycle The most common default se...

Page 6: ...s in Placing unit into service to step valve through all 4 cycles but do not open bypass valve When this procedure is performed with the bypass closed it will relieve any water pressure on the unit Re...