Installation and connection
05.06.2015
17 / 80
Copyright
2013 by: WATERKOTTE GmbH. Subject to changes.
6
Installation and connection
6.1
Installation and connection of indoor unit
To make hydraulic connections, you must use the supplied material (con-
necting lines and gaskets).
During assembly of connecting lines, use an according tool as brace to
prevent damage to the heat distribution station.
Installation of heat distribution station / storage tank must be performed at
a flat and horizontal surface.
Wall clearance in front: at least 1000 mm.
Because all connections are on the rear panel, choose a installation dis-
tance from the wall (rear, right side, left side), which is also ensures ac-
cess in case of repair.
Recommendation:
Wall clearance left, right and on top must be at least 400 mm.
Wall clearance in rear must be at least 200 mm.
Wall clearance in front: at least 1.000 mm.
Figure 3: Recommendation - Installation distance from the wall