background image

The Cube Technical Manual - Version 1, May 2014

16

17

Maintenance and Servicing

•  The Cube must be serviced every 12 months, but we strongly recommend 

  the UV lamp and filters be changed every six months.

•  The Cube may require any calcium build up in the hot tank to be removed, 

  this depends on the local water conditions.

•  No paperwork or cleaning records should be stored inside the Cube.

•   To reset the filter timer, hold down the hot and cold icons simultaneously 

  for 10 seconds.

The items required to complete this procedure are:

•  Rubber Gloves

•  Phillips Screwdriver

•  Replacement filter cartridge(s)

•  A container that can hold 5 litres

•  New 13 watt UV lamp

•  Non-abrasive anti-bacterial wipe or cloth

1. 

  Put on the rubber gloves to minimise the chance of any contamination to the 

machine and to protect yourself whilst the servicing procedure is being carried out.

2.

 You will need to stop the water supply to the machine by turning the isolation 

valve to the off position and releasing the pressure by selecting the cold water 

option until the water stops being dispensed.

3.

 Isolate the power to the Cube by turning the red and green power switches off, 

these are located at the rear of the machine. Remove the power lead as a second 

safety precaution.

4. 

Remove the top cover from the Cube by undoing the two screws located at the 

back of the machine, then slide the panel backwards and lift up.

5.

 Take out the filter by un-clicking the loop at the top of the filter housing and 

pulling it in an upward motion. If there are two filters in the machine then both of 

these need to be removed. 

6.

 Unscrew the filter housing to expose the used filter cartridge. This cartridge can 

then be removed from the filter housing and replaced by a new one. Return the 

filter(s) into the correct position in the machine; ensuring that it is pushed firmly into 

place as the valves will be reopened by the insertion of the filter. 

7. 

Remove the UV lamp by unplugging the UV loom, and pulling the lamp upwards.

8.

 Examine the UV loom for any discolouration or wear, if there is any visible remove 

the loom and replace with a new one.

9.

 Reconnect and replace the UV lamp assembly, making sure not to touch the new 

UV lamp with bare hands as this will shorten the life of the lamp.

10.

Inspect all of the electrical and water connections on the machine, and take any 

action necessary to prevent a fault from occurring.

11. 

Check the faucet nipple for any calcium build up or any visible damage and clean 

or replace it if necessary.

12.

Reassemble the machine and secure all panels with screws.

13.

Check that the air gap around the machine is sufficient and there is nothing 

blocking the ventilation.

14.

Reconnect the power to the machine and turn the red switch at the rear of the 

machine to the ‘on’ position. Turn on the water supply. 

15.

The filter(s) now need to be flushed. Do this by selecting the ambient water option 

and dispensing 10 liters of water through the machine. This will sufficiently generate 

the filter and remove any excess black carbon fines.

16.

The green heater and compressor switch can now be turned on.

17.

 Select the hot icon, then select and hold the main dispense button immediately 

after selecting the hot icon.

18.

 Dispense at least 200ml of hot water.

19.

 The machine will now begin to heat / chill the water.

20.

 Clean the outside of the machine with a non-abrasive anti-bacterial wipe or 

cloth.

21.

 Taste the water one final time and check it is cooling and heating the water.

SANITISING

You will need the following items:

•  A Phillips screwdriver

•  Rubber gloves

•  Aqua Dosa sanitisation fluid

•  Suitable test strips to work with your sanitisation fluid

•  Non-abrasive anti-bacterial wipe or cloth

•  A container that can hold 5 litres

1.

 Put on the rubber gloves to minimise the chance of any contamination to the 

machine and to protect yourself whilst the sanitisation procedure is being carried 

out.

2.

 You will need to stop the water supply to the machine by turning the isolation 

valve to the off position and releasing the pressure by selecting the cold water 

option until the water stops being dispensed.

3.

 Isolate the power to the Cube by turning the red and green power switches off, 

these are located at the rear of the machine. Remove the power lead as a second 

safety precaution. 

Summary of Contents for WL Cube Firewall

Page 1: ...WL Cube Firewall Technical Manual VERSION 1...

Page 2: ...10 The appliance is to be supplied through a residual current device RCD having a rated residual operating current not exceeding 30mA 11 This appliance is intended to be used in household and similar...

Page 3: ...any kinds of different filter combinations available from Waterlogic to suit local water conditions FIREWALL CHAMBER The Firewall chamber incorporates the in Faucet UV and is made of aluminium and is...

Page 4: ...the quartz spiral cleaned by using an ultrasonic bath if needed PCB The PCB Printed Circuit Board is the control unit for the Cube it is responsible for the functions of all the mechanical and electri...

Page 5: ...a trip hazard Keep them off the floor Take care not to allow the power lead to get wet If the lead gets wet it must not be used The Cube Technical Manual Version 1 May 2014 WL Cube Flow Diagram Cold...

Page 6: ...rocedures 1 Mount the Cube on a firm level surface so the machine cannot topple or fall over A 50mm air gap is required the whole way around the machine to allow for sufficient ventilation The Cube mu...

Page 7: ...The Cube should be sanitized at installation INSTALLATION KIT The Cube must be installed according to the local guidelines and it is advised that an installation kit be used A pressure reducing valve...

Page 8: ...Always place cup mug in the centre of the drip tray Always use a ceramic cup or a cup suitable for use with hot water Do not hold cup or place hands in dispensing area whilst dispensing water Do not...

Page 9: ...if there is any visible remove the loom and replace with a new one 9 Reconnect and replace the UV lamp assembly making sure not to touch the new UV lamp with bare hands as this will shorten the life...

Page 10: ...16 The machine will now begin to heat chill the water 17 Inspect the faucet nipple and clean or replace if it is damaged or if there any calcium built up around it 18 Using the antibacterial wipes su...

Page 11: ...panels of the machine including the drip tray and grill ADVISORY ICONS HOT WATER Press and hold the hot water icon for 3 seconds until the icon has illuminated orange select the dispense button and ho...

Page 12: ...rrectly and being turned on and off when you select the cold option 5 There is cold water flow but hot water is not flowing This may be due to calcium build up in the hot tank or the hot water outlet...

Page 13: ...t and continual improvement and therefore reserves the right to change specifications without prior notice other than in the case of significant changes Description Cube 120V HCA Cube 230V HCA Machine...

Page 14: ...into the surface of our products giving them built in sustainable antimicrobial protection BioCote s silver technology has been tested by an independent laboratory to show its ability to inhibit the g...

Page 15: ...rsion 1 May 2014 28 29 Electrical Wiring Diagram 230V Dip Switch Setup DANGER HIGH VOLTAGES PRESENT ON THIS PCB CARE MUST BE TAKEN WHEN LIVE TESTING THE CUBE MAIN PCB DIP SWITCHES 1 2 WITH INSTRUCTION...

Page 16: ...ERATURE SETTING Cold water temp range 5 c 10 c 15 c When reading this document please note the white coloring on the diagrams indicate the required position of the switch to determine the setting UV 1...

Page 17: ...Blue O D 1 4 13 JG Equal Tee Connector 1 4 14 JG Equal Elbow Connector 1 4 15 JG LLD PE Tube Blue O D 1 4 16 Solenoid Valve 24 DC Single Spring Load 17 JG Stem Elbow Connector 1 4 1 4 18 Drain valve...

Page 18: ...nector 1 4 36 JG LLD PE Tube Blue O D 1 4 37 JG LLD PE Tube Blue O D 1 4 38 Solenoid Valve 24 DC Single Spring Load 39 JG Equal Tee Connector 1 4 40 JG Stem Elbow Connector 1 4 1 4 41 JG Equal Tee Con...

Page 19: ...stem Elbow connector 15 Solenoid Valve 24 DC Single Spring Load 16 Cube cold tank 1 4 Litre 17 Compressor 18 Domestic Filter Dryer Chinese 19 WL Cube Side panel right Silver 20 BulkHead Fitting 1 4 x...

Page 20: ...use WL Label 37 Hot Cold Solenoid Valve 24V 300mm CUBE 38 1 4 Equal Tee Connector ST 39 UV 15 W Electronic Ballast Ver 3 40 Power Transformer 41 WL Cube Electronics cover Black 42 WL Cube UI Label WL...

Page 21: ...eacon Court Sandyford Dublin 18 Ireland www waterlogic com Waterlogic USA 11710 Stonegate Circle Omaha NE 68164 Speak to a Water Expert Rest of the world exportsales waterlogic com 353 1 293 1960 USA...

Reviews: