Connecting the Extension Cable
1
4
3
2
Dual Priming Pumps—12V
Use the illustration and instructions to connect the
extension cable to the priming pump.
1 Connect the white wire from the extension
cable to the signal terminal on the priming pump
terminal. Torque the nut to
1.5 ft-lb (2 N∙m).
2 Connect the red wire from the extension cable
to the power terminal. Torque the nut to
4.5 ft-lb
(6 N∙m).
3 Connect the black wire from the extension
cable to the ground terminal. Torque the nut to
4.5 ft-lb (6 N∙m).
4 Use the included jumper wire to connect both
signal terminals. Torque the nut to
1.5 ft-lb
(2 N∙m).
Note:
If the included jumper wire is shorter than
required for your application, fabricate
a jumper wire of the appropriate length
by sourcing a white, 18 AWG wire that
meets or exceeds SAE J1128-GPT
standard. Terminate each end with a #10
ring terminal.