Modulex EXT Commercial Series Boilers User Manual
CHAPTER 4: Installation Instructions
OMM-0095_0H
AERCO International, Inc.
•
100 Oritani Dr.
•
Blauvelt, NY 10913
Page
43
of
144
GF-139
Phone: 800-526-0288
09/15/2017
Please note that 10” and 12” PVC can be heavy and expensive. Alternative vent materials, such
as AL29-4C or polypropylene should be considered prior to installation.
The plastic components, primers and glues of the certified vent system must be from a single
system manufacturer and not mixed with other manufacturer’s vent system parts.
The Inspection Port should be plugged with an appropriate plug (not included).
Figure 4-15: Installed Flue Exhaust Diameter Reduction Adaptor Kit
4.21 COMBUSTION AIR AND VENTILATION OPENINGS
Provisions for combustion and ventilation air must be made in accordance with
section 5.3
, Air
for
Combustion and Ventilation, of the National Flue Gas Code
,
ANSI Z223.1/NFPA 54.
, or
Sections 7.2, 7.3
or
7.4
of
CAN/CSA-B149.1-05
, installation codes, or applicable provisions of
the local building codes.
4.21.1 Insufficient Ventilation and Combustion Air
BOILER DAMAGE AND OPERATIONAL FAILURES may occur due to insufficient or improper
openings for combustion air and/or ventilation of the boiler room.
Provisions for combustion air and ventilation are always required, regardless of whether the
combustion air is taken from the outside (sealed combustion) or inside (room air used as
combustion air).
Insufficient ventilation of the boiler room can lead to high air temperatures. This can result in
boiler damage. Note the following:
•
Make sure that intake and exhaust openings are sufficiently sized and no reduction or closure
of any openings takes place.
•
When a combustion air or ventilation problem is not resolved, do not operate the boiler.
INSTALL FLUE
PIPING TO ADAPTER
WITH RTV LIQUID
SILICONE AND
WORM-DRIVEN
HOSE CLAMP
FLUE VENT PIPE
ADAPTER ASSEMBLY
EUROPEAN TO AMERICAN
STANDARD FLUE ADAPTER
Test Nipple
should be
installed
within first
3 feet of
flue start.
3 feet
(914.4 mm)