Dosing Device Foamdos V6
Index: 01
Date modified: 26/08/2019
OI No.: BA DW 025-00 Foamdos V6 EN.DOCX
Page 15 of 37
Connect the inlet line
For the connection of the inlet line, we recommend
tempered water
or a thermostatic mixer
, so that the
water temperature for flushing is comfortable.
Install the inlet line to the dosing device.
Connect the foam line
The foam line should be as short as possible, a maximum of 10 m is possible. The foam line should have an
inside diameter of 10-13 mm.
The foam line from the dosing device to the foam dispenser can be connected in 2 different variants:
1.
Standard foam line
Install the foam line up to the connection bend for the shower hose of the hand-held shower head.
Connect the shower hose and the hand-held shower head to the wall mounting bend.
2.
Foam line with drain valve
If the foam line must be installed at an incline and exceeds a length of 1m, the use of a drain valve
(accessory) is recommended.
Install the foam line with branch for the drain valve, up to the connection bend for the shower hose
of the hand-held shower head.
Install the drain valve in such a way that the
line can run empty
. This prevents cold water from
coming out of the foam line during the next operation.
Connect the drain valve to the waste water pipe via a funnel drain
(system separation).
Connect the shower hose and the hand-held shower head to the wall mounting bend.
Variants for the foam dispenser
The foam dispenser is available as:
a)
movable hand-held shower head.
(option)
or as
b)
fixed foam dispenser
(on-site service)
Install line from system separator to drain, at least d40mm
Figure 10, Standard installation plan with foam dispenser
control cable
co
nc
en
tr
at
e
ho
se
foam concentrate
38°C recommended
to sewer
Inlet