GENERAL INFORMATION
Bracket Spacing Requirements
This chart applies to straight sections of track only.
All ceiling mounted track sections must have a minimum of three (3) brackets.
All curved tracks must have a minimum of three (3) brackets.
Make sure that all edges of tracks are without debris or excess powder coat in the running surfaces to
ensure smooth GoLift/trolley traversing.
GoLift
Ceiling & Gantry Track Span
Lift Capacity (
kg/st
) Regular Track (
cm
) Double Track (
cm
)
Triple Track (
cm
)
181/28
233
378
665
318/50
152
270
480
454/72
110
236
420
Note: Any ceiling track must have a minimum 3 brackets.
Recommended for regular track to put 3 in bracket every 3ft
1) Service load = rated lifting capacity (400, 700, 1000 lbs).
2) Factored load = 125% test load of the rated lifting capacity (400 X 1.25% = 500 lbs)
3) Maximum deflection = L/200 (where “L” is the span between supports). A 96” span = 0.48”
maximum deflection. Note: deflection should only be measured under Service Load and not the
Factored Load.
GoLift
Installation Manual Rev. 27-Mar-2017
Summary of Contents for GoLift
Page 1: ...GoLift Installation Manual Rev 27 Mar 2017 1 GoLift Hoist INSTALLATION GUIDANCE...
Page 6: ...6 Figure 1 Top Down Wood Joist Installation GoLift Installation Manual Rev 27 Mar 2017...
Page 7: ...7 GoLift Installation Manual Rev 27 Mar 2017...
Page 13: ...13 Figure 4 Multiple Anchor Attachments GoLift Installation Manual Rev 27 Mar 2017...
Page 14: ...14 Figure 5 Concrete Slab Installation GoLift Installation Manual Rev 27 Mar 2017...
Page 16: ...16 Figure 6 Epoxy Anchors in Hollow Core Concrete GoLift Installation Manual Rev 27 Mar 2017...
Page 18: ...18 Figure 8 Attaching to Steel I Beams GoLift Installation Manual Rev 27 Mar 2017...