Preconditions for the commissioning

 

The installation work has been made according to the  

“Installation” chapter of this user manual.

 

– The ground around the PV AC

 combiner box is firm and 

easily accessible so that work can be done safe.

 

Wear appropriate clothes and personal protective equip-

ment.

 

Use appropriate tools with the correct insulation.

A multimeter is necessary in order to verify the 

absence of voltage in the live parts of the com-

biner box.

 

► Check that the multimeter is capable to read 

the maximum voltage of the string inverter 

output and the maximum 

current flowing 

through before starting any operation.

DANGER

Imminent risk of life!

High voltages up to 800 V AC are present in 

the live parts. Touching live parts can result in 

death or serious injury due to electric shock.

 

► Before starting any work in the PV AC 

combiner box:

 

– disconnect the main switch

 

– ensure that there are no fuses inserted 

into the fuse-holders.

 

Ensure that nobody reconnects the unit 

while work is not finished or any operator 

is still working.

 

Ensure that no voltage is present in parts 

that are going to be manipulated or that 

could be accessible.

 

Do not touch live components.

 

► If specific live parts cannot be insulated or 

disconnected, it is mandatory to use addi-

tional safety elements to avoid any risk to 

persons or equipment.

6.1  Main indications and inspections

It is recommended to carry out a general inspection on the 

PV AC combiner box and the status of the installation be-

fore commencing operation.

The installation must comply with either local and interna-

tional regulations.

Visual inspection

Check the following issues:

 

– All cables are in good condition.

 

– There are no hazards around the installation that could 

create any damage.

 

– The cables are connected to the correct phase and ac-

cording to electrical drawing provided.

 

The enclosure is firmly fixed to the structure, all mount

-

ing elements are tightened properly.

 

– The door of the enclosure is properly closed and the 

seal fits all around the door to provide the insulation. As 

a check press the door while locking the key-locks a few 

times.

 

– The cable glands are tightened correctly.

 

– The grounding cable is connected through its own cable 

gland and the cable gland is tightened correctly.

 

Check the correct status of the SPD. The viewing win

-

dow should be in green colour.

Additional inspections issues for combiner boxes 

with Energy meter

 

The RS485 wire is correctly connected to the specific 

terminals inside the combiner box or alternatively to the 

D650 connector through its own cable gland.

 

– The cable gland for communications cable is tightened 

correctly.

Measurements

DANGER

Imminent risk of life!

High voltages up to 800 V AC are present in 

the live parts. Touching live parts can result in 

death or serious injury due to electric shock.

 

► Before starting any work in the 

PV AC combiner box:

 

– disconnect the main switch

 

– ensure that there 

is no current flowing 

through any of the wires of the box. 

6  Commissioning

Summary of Contents for 40201S2V4C2A0ES

Page 1: ...PV AC combiner box Operating instructions...

Page 2: ...4000003077 00 02 2021 2...

Page 3: ...e 11 4 4 Establishing connections 11 5 Installation 12 5 1 Installation site 12 5 2 Positioning of the combiner box 12 5 3 Fixation 12 5 4 Installing the combiner box 13 5 5 Inserting the fuses 15 5 6...

Page 4: ...or death if you do not follow the instructions given in this manual CAUTION Risk of injury Notices with the signal word CAUTION warn you of situations which may result in in jury if you do not follow...

Page 5: ...ng string If the installation regulations are violated all warranty and liability claims are void If a malfunction on a PV AC combiner box cannot be fixed after following the recommended measures the...

Page 6: ...ut of this product ranges from 400 V to a maximum input voltage of 800 V per string inverter The necessary AC inverter outputs are to be connected at the PV AC combiner box inputs whereas one AC main...

Page 7: ...n 5 1 3 4 2 Figure 3 2 Main components of the PV AC combiner box example 1 Circuit breaker or fuses 2 Ground terminal 3 Output terminals 4 Surge protection device 5 End bracket Figure 3 3 Inputs and o...

Page 8: ...protection device SPD Figure 3 6 Surge protection device The surge protection device as an optional component has been selected corresponding to the customers require ments and in accordance with the...

Page 9: ...olt and nut M12 NH 3 240 mm2 300 mm2 Bolt and nut M12 SPD Cross section Screw conection 2 5 mm2 35 mm2 Conductor cross section Tolerance of stripping length 4 mm2 1 mm 6 10 mm2 1 5 mm 16 mm2 2 mm In o...

Page 10: ...V AC standard other options on demand Short circuit and over current protections Fuse blocks 3p with breaking capacity Rated AC current per input 135 A Breaking capacity 120 kA kA with fuses Enclosure...

Page 11: ...Relative humidity 0 to 50 ATTENTION Material damage The AC box must be stored lying flat on the rear side Otherwise the cable glands and connectors at the bottom of the enclosure can be damaged In the...

Page 12: ...etime or damage to the internal components of the com biner box To protect the combiner box against direct sun light and rain you can install it under the pho tovoltaic modules or a protective canopy...

Page 13: ...se the cable glands and connectors at the bottom of the enclosure can be damaged Remove the combiner box from the original packaging Measure the exact distances between the drilling holes and mark the...

Page 14: ...5 D 1090 1 This table is a reference For specific measure of your product please refer to the documentation delivered with the product Enclosures mounting lugs and fixing points1 Size Dimensions HxWxD...

Page 15: ...e into the combiner box Make sure the wires pass through their designated cable gland with their thread in correct position Strip the conductor for the input cross section according to the ring termin...

Page 16: ...regard the following steps to prepare the aluminium conductors Scrape the stripped end of the conductor carefully e g with a knife to remove the layer of oxide Do not use brushes files or emery paper...

Page 17: ...ded to carry out a general inspection on the PV AC combiner box and the status of the installation be fore commencing operation The installation must comply with either local and interna tional regula...

Page 18: ...ed by Weid m ller within each individual PV AC combiner box In case the PV AC combiner box has been provided without fuses please use the au thorised fuses or contact with your Weidm ller representati...

Page 19: ...oard same model and rate Before replacing fuses verify that there is no electrical issue active in the circuit which could cause the blowing of the new fuse Use the appropriate tool to extract the dam...

Page 20: ...ing agents solvents and high pressure cleaners Use a cloth moistened with clear water for cleaning Clean the enclosure at regular intervals so that the warning symbols are always clearly visible Only...

Page 21: ...ter or humidity inside the enclosure Regard the tightening torques in the specific docu mentation inside each PV AC combiner box Check the cable glands and retighten them if needed Surge protection ar...

Page 22: ...easure voltage Check the voltage of the strings by using the test ing points in the terminals General inspection Check that there are no burn marks on the termi nals 9 2 Service If you have any questi...

Reviews: