Final inspection OXYWAY Fix I, OXYWAY Fix III
7.3 Required test and auxiliary
equipment
• Leak detection spray
• LPA cap, G 3/8"
• Brush
• Cloth
• LPA shut-off valve, G 3/8" internal thread - G 3/8" external
thread
• LPA cap, UNF 9/16"
• LPA adapter, G 3/8" internal thread - CGA V-5 external thread
(UNF 9/16")
• Set, supply test
• Special kit, ventilation test kit and pressure reducer Flow
• Oxygen cylinder
• Testing devices:
Flow measuring tube 0 to 20 l/min
Flow measuring tube 0 to 220 l/min
Pressure gauge
Or
Ventilator tester
7.4 Preparing the final inspection
1. Enter the serial number of the pressure reducer in the test report.
2. Check the pressure reducer for external damage.
Requirement:
The pressure reducer shows no signs of external damage.
3. Check the label
on the pressure reducer
(see "18.5 Labels for pressure reducers", page 242)
.
Requirement:
The label
on the pressure reducer is present and legible.
4. Check the serial number embossed on the pressure reducer
for legibility.
Requirement:
The embossed serial number is legible.
5. Check the connection thread on the pressure reducer.
To do so:
• Screw the cap
Or
Screw the adapter
.