9.
MPM:
Mate the connectors with a push and twist motion (bayonet style)
10.
MPM:
Reinstall the shroud
11.
MPM:
Turn on power to the MPM
12.
MPM:
Confirm that the following LEDs are lit
a. LED 1
– power
b. LED 2
– System running
13.
RSP:
Confirm that the following LEDs are lit
a. LED 1
– power
b. LED 2
– System running
14. If all above LEDs are lit, the configuration process may begin, if not contact the
Synertrex Operations team for assistance with troubleshooting and/or refer to the
troubleshooting guide within the IOM Manual.