Installation
5.2 Installation prerequisites
5
5.2
Installation prerequisites
Dimensions, total weight and possibly fastening bores for the machine are
specified in the layout on the system-dependant documentation.
Check prior to installation whether the dimensions of the installation site and building
conditions correspond to the necessary prerequisites and measurement specification in
the planning documents.
Particularly ensure that:
•
The substructure of the installation site must be statically measured to an adequate
degree to ensure that it can support the operating weight of the machine.
•
The drives of the locking stations, belt sections and corner units, as well as the sen-
sors should remain easily accessible for maintenance work and the motor vents
should have a minimum distance of 100 mm from other modules.
Base frame:
If delivered with base frames, the base frames are set up and aligned via levelling feet. At
the work height specified in the layout an adjusting range for the levelling feet of
+40 mm / -10 mm is possible.
Base frame or base plate:
If delivered with base frame or base plate particularly ensure that
•
The supporting floor is level and rigid.
`
Maximum permissible evenness deviation over the entire placement surface:
0.1 mm.