Press
ENTER
on the display for 3 seconds. The Menu code will appear as 000. This does not change. Press
ENTER
again. SERVICE
SCHEDULE RESET will be displayed. Using the right arrow key
scroll to the selection of year or hours. Select enter to reset the
mode you are in. Use the up
▲ or down ▼ arrow key for each adjustment then select
ENTER
when reset is complete.
PART 11 – START-UP PROCEDURES FOR INSTALLER
Table 23
– NOTE:
It is important to note that the user can adjust the heat curve down by lowering the central heating temperature.
A. BOILER CONTROL STATUS MENU
The boiler control also has the ability to review the status of the system. To access the status screens, simply press the right arrow
.
Once the first value is displayed, press the up arrow
▲ or down arrow ▼ to access additional information. At any point you may press
the RESET button to exit the status screen. Listed below are the status screens.
SCREEN
DESCRIPTION
SUPPLY SEN 180
o
F
RETURN SEN 150
o
F
This screen is displayed after pressing the
key as described above. This shows the actual temperature that
the supply and return sensors are measuring. NOTE: If the boiler is configured to use a 0
– 10 volt input, the
return sensor is disabled and the second line of the display will be blank.
Press the
▼ key once.
CH SET 180
o
F
SUPPLY 122
o
F
The screen displays the current central heating temperature set point on the top line. NOTE: This temperature
set point may vary from what was set in the boiler settings if an outdoor sensor is used. The actual temperature
measured by the supply sensor is displayed on the bottom line.
Press the
▼ key once.
CH DEMAND OFF
BOILER
This screen displays the central heat demand set for the cascade system.
Press the
▼ key once.
0-10 SIGNL ON
*
Shows if 0
– 10 volt is enabled.
Press the
▼ key once.
CAS SET 190
o
F
SYSTEM 112
o
F
NOTE:
This screen will appear only when set in Master Boiler mode.
This screen displays the cascade set point (maximum 190
o
F) on the top line. The system sensor value reading is
on the second line. The control will cascade the boilers up to this set point depending on demand.
Press the
▼ key once.
Summary of Contents for WBCNG399W
Page 14: ...14 WHL 016 REV 12 18 14 SPECIFICATIONS AND DIMENSIONS Figure 2 Specifications and Dimensions ...
Page 24: ...24 WHL 016 REV 12 18 14 Figure 8 Piping Symbol Legend ...
Page 59: ...59 WHL 016 REV 12 18 14 Figure 32 Cascade Master and Follower Wiring ...
Page 60: ...60 WHL 016 REV 12 18 14 Figure 33 Internal Connection Diagram LP 293 J ...
Page 83: ...83 WHL 016 REV 12 18 14 055 080 110 PARTS BREAKDOWN Figure 36 Replacement Parts LP 387 J ...
Page 85: ...85 WHL 016 REV 12 18 14 155 199 285 399 PARTS BREAKDOWN ...
Page 86: ...86 WHL 016 REV 12 18 14 Figure 38 Replacement Parts LP 387 KK ...
Page 87: ...87 WHL 016 REV 12 18 14 155 199 285 399 MODEL PARTS BREAKDOWN ...
Page 91: ...91 WHL 016 REV 12 18 14 ...
Page 92: ...92 WHL 016 REV 12 18 14 ...