7
OPM-160/A
PREPARING THE UNIT
START-UP CHECK LIST
A Start-Up Completion & Warranty Validation Form was
sent along with this manual. This must be completed and
returned to WINCO Inc. within 180 days of the factory
invoice date.
If this form is not returned, the Warranty may be voided.
UNPACKING
1. As you receive your unit, it is critical to check it for any
damage. If any damage is noted, it is easiest to refuse the
shipment and let WINCO take care of the freight claim. If
you sign for the unit, the transfer of the ownership
requires that you file the freight claim
2. Before proceeding with the preparations of your new
generator for operation, take a couple of minutes to
ensure the unit you have received is the correct model
and review the specification pages in this manual to
ensure that this unit meets your job requirements.
CAUTION: EQUIPMENT DAMAGE
These units are shipped with oil and a 50/50 mix of
coolant. Be sure to check all fluid levels before operating.
See engine manufacturer’s instruction manual for
recommended oil requirements before initial starting.
Once generator set is on-site:
1. Carefully remove the crate.
2. After inspecting the engine-generator for external,
physical damage, locate and check the following items
packed with the unit:
a. Installation and Operator’s Manual.
b. Engine manufacturer’s instruction manual.
c. Start-up and warranty validation form.
d. Battery hold-down brackets & hardware.
e. Unit components or accessory items shipped loose
for on-site installation.
f. Optional accessories.
3. Remove main frame hold-down bolts.
4. Unit can now be lifted from shipping rails.