background image

3

7. Using the supplied dual coax cable, connect the ends with red heat 

shrink wrap to Port 1 on LNB and the black coax cables to Port 2 on 
LNB. Tighten each cable until fingertight, and then use a 7/16”wrench 
to tighten a quarter turn more.

8. Slide the LNB into the integrated adapter, and re-install the two screws 

(removed earlier) through the integrated adapter and LNB.

9. Connect the red heat shrink wrapped coax to Port C on the TRAV’LER 

turret and the black coax cable to Port A on the TRAV’LER turret. 
Tighten each cable until fingertight, and then use a 7/16”wrench to 
tighten a quarter turn more.

10. Place the p-clamp on the sheathed cables, and make sure the hole 

in the p-clamp is positioned above the cables. The p-clamp must be 
installed 14 inches from the ends of the sheathed cables. This point on 
the cable may already be marked by a zip tie, mark, or tape.

11. Align the hole in the p-clamp with the hole in the lift arm. Install the 

screw through the p-clamp and lift arm, and tighten.

Model RP-SK45 DIRECTV

®

 Slimline Repl. Cables

1. Remove and set aside the 

four nuts and bolts holding 
the LNB guard to the feed 
arm. Then, slide the LNB 
guard down the feed arm and 
toward the reflector.

2. Remove and set aside the two 

screws holding the LNB to the 
feed arm. 

3. Carefully slide the LNB out from the feed arm. Disconnect the four 

coax cables from the LNB using a 

7

/

16

” wrench.

4. Using a  

7

/

16

” wrench, disconnect the four cables from the coax ports 

on the top of the turret. 

5. Using a 

5

/

16

 wrench, remove the screw holding the p-clamp to the 

lift arm, and detach the p-clamp from the lift arm. Set the screw and 
p-clamp aside; you will need these later. 

6. Once disconnected, remove the sheathed cables.

Screws holding 

LNB to feed arm

Bolts holding 

LNB guard 

to feed arm

LNB guard

Summary of Contents for TRAV'LER RP-SK41

Page 1: ...llite TV Antenna Replacement Sheathed Cables Instruction Manual Models RP SK41 RP SK42 RP SK45 RP SK47 and RP SK49 For help email help winegard com or call 1 800 788 4417 www winegard com mobile 2452298 2452298 Rev2 10 19 ...

Page 2: ... Carefully slide the LNB out from the integrated adapter Disconnect the three cables from the LNB using a 7 16 wrench 3 Using a 7 16 wrench disconnect the three cables from the coax ports on the top of the turret 4 Using a 5 16 wrench remove the screw holding the p clamp to the lift arm and detach the p clamp from the lift arm Set the screw and p clamp aside you will need these later 5 Once discon...

Page 3: ...id Replacement Cables 1 Remove and set aside the two screws from the wider end of the underside of the integrated adapter 2 Carefully slide the LNB out from the integrated adapter Disconnect the three cables from the LNB using a 7 16 wrench 3 Using a 7 16 wrench disconnect the three cables from the coax ports on the top of the turret 4 Using a 5 16 wrench remove the screw holding the p clamp to th...

Page 4: ...d cables This point on the cable may already be marked by a zip tie mark or tape 11 Align the hole in the p clamp with the hole in the lift arm Install the screw through the p clamp and lift arm and tighten Model RP SK45 DIRECTV Slimline Repl Cables 1 Remove and set aside the four nuts and bolts holding the LNB guard to the feed arm Then slide the LNB guard down the feed arm and toward the reflect...

Page 5: ... front of the LNB guard should be in front of the LNB and should not be touching the LNB 11 Install the four bolts through the four holes in the LNB guard Thread a nut onto each bolt and tighten 12 Connect the other ends of the sheathed cables to coax ports A D on the top of the turret Tighten each cable until fingertight and then use a 7 16 wrench to tighten a quarter turn more 13 Place the p cla...

Page 6: ...side you will need these later 6 Once disconnected remove the sheathed cables 7 Run the replacement sheathed cables through the feed arm 8 Connect the four cables running through the feed arm to the four ports on the LNB The cables can be connected in any order Tighten each cable until fingertight and then use a 7 16 wrench to tighten a quarter turn more 9 Slide the LNB into the feed arm and re in...

Page 7: ...ide the four nuts and bolts holding the LNB guard to the feed arm Then slide the LNB guard down the feed arm and toward the reflector 2 Remove and set aside the two screws holding the LNB to the feed arm 3 Carefully slide the LNB out from the feed arm Disconnect the coax cable from the LNB using a 7 16 wrench 4 Using a 7 16 wrench disconnect the cable from port C on the top of the turret 5 Using a...

Page 8: ... Align the hole in the p clamp with the hole in the lift arm Install the screw through the p clamp and lift arm and tighten Stowing the Antenna 1 Plug in the interface box 2 Press and hold POWER for two seconds to turn on the interface box Then press the Power button again to stow the antenna 7 P clamp installed 14 from ends of sheathed cable next to zip tie on sheathed cable Disclaimer Although e...

Reviews: