10.5
Examine the rail unit for leakage
Periodicity
Description
Unscheduled
Duration for performing preliminary requirements
0.0 man-hours
Duration for performing the procedure
1.0 man-hours
Duration for performing the requirements after job completion
0.0 man-hours
Personnel
Description
Specialization
QTY
Engine crew
Basic
1
Support equipment
Description
Part No.
CSN
QTY
None
Supplies
Description
QTY
None
Spare Parts
Description
Part No.
CSN
QTY
None
SAFETY PRECAUTIONS
CAUTION
Injury Hazard: Always put on gloves and safety goggles when you do work on hot or
pressurized components. Fuel can come out as a spray and cause injury.
PRELIMINARY OPERATIONS
•
None
X72-B
AA00-0000-00AAA-311E-A
Operation Manual
Examine the rail unit for leakage
Winterthur Gas & Diesel Ltd.
- 416 -
Issue 003 2021-12