9.5
Clean the scavenge air cooler during operation
Periodicity
Description
Weeks
1
Duration for performing preliminary requirements
0.0 man-hours
Duration for performing the procedure
1.0 man-hours
Duration for performing the requirements after job completion
0.0 man-hours
Personnel
Description
Specialization
QTY
Engine crew
Intermediate
1
Support equipment
Description
Part No.
CSN
QTY
None
Supplies
Description
QTY
Cleaning fluid
A/R
Spare Parts
Description
Part No.
CSN
QTY
None
SAFETY PRECAUTIONS
•
None
PRELIMINARY OPERATIONS
•
None