9.7
Running-in of new components
Periodicity
Description
Unscheduled
Duration for performing Preliminary requirements
0.0 man-hours
Duration for performing the Procedure
72.0 man-hours
Duration for performing the Requirements after job completion
0.0 man-hours
Personnel
Description
Specialization
QTY
Engine crew
Intermediate
1
Support equipment
Description
Part No.
CSN
QTY
None
Supplies
Description
QTY
None
Spare Parts
Description
Part No.
CSN
QTY
None
SAFETY PRECAUTIONS
•
None
PRELIMINARY OPERATIONS
•
This procedure is only applicable, if you have done an overhaul or you have installed new
components of the piston running system.
X52
AA00-0000-00AAA-950A-A
Operation Manual
Running-in of new components
Winterthur Gas & Diesel Ltd.
- 346 -
Issue 002 2018-11