5.3 Decommissioning
The work process during decommissioning depends on whether the high
pressure cleaner is only going to be taken out of operation temporarily or
for longer periods or permanently
5.3.1 Temporary decommissioning
1.
Relieve the pressure as described in chap. 5.2 on page 30.
2.
Set down the high pressure cleaner gun in the mounting provided for
this on the frame of the high pressure cleaner.
5.3.2
Long-term or final decommissioning
1.
Relieve the pressure as described in chap. 5.2 on page 30.
2.
Set down the high pressure cleaner gun in the mounting provided for
this on the frame of the high pressure cleaner.
3.
Shut off the air supply on the compressor.
4.
Relieve the pressure in the compressed air line from the compressor
to the compressed air connection of the high pressure cleaner.
5.
Disconnect the compressed air line from the compressed air
connection of the high pressure cleaner.
5.4 Storage
Store the device in a place where it is protected against dirt, moisture,
frost, and heat.
Storage temperature
minimum
maximum
0 °C
32 °F
40 °C
104 °F
5.5 Disposal
It is necessary to collect residues of cleaning agents, oils, greases and
other chemical substances according to the legal regulations for recycling
or disposal. The official local waste water protection laws apply.
At the end of the device's use, it must be put out of use, disassembled
and disposed of according to the legal regulations.
Disassemble the device and separate the materials - metals must be
taken to a scrap metal depot, plastic parts can be disposed of with
household waste.