Translation of the original Operation Manual
2-3
•1307_PU280_SV1018DV1020_BAoDB_en•ski
en
Safety Information
➤
Never spray cleaning agent or cleaning agent containing materials into cone-
top cans or drums with bunghole!
➤
Always use open containers. Stand the containers on a grounded surface.
When using metal containers avoid contact between spray gun and container
wall, because of possible electrostatic charging.
The high flow velocities associated with the Airless spraying method may
cause static charging. Static discharges can cause fire and explosion.
The original
DUOMIX PU
280 is earthed via the electrical connection as
standard.
➤
Never operate the unit outside in case of a thunderstorm.
➤
Because of the generated electrostatic charging you should only use conduc
-
tive material hoses. All original
material hoses are conductive and per
-
fectly matched to our equipment. The maximum permitted working pressures
of the hoses must be higher than or equal the maximum operating pressure of
the corresponding dual component system.
➤
Switch off all heaters when working with cleaning agents in the material circuit
(e.g. complete cleaning).
Complete cleaning must only be performed after the system has cooled down.
➤
The system must NOT be operated in explosion protection zones!
Spraying equipment designed without explosion protection must not be used in
workshops that come under the explosion protection ordinance.
Juveniles under the age of 16 have no permission to operate this equipment.
The owner of the machine must ensure that the user manual is made available to
the user and make sure that the user has read and understood its contents.
Activity
Qualification of personnel
Setup work
instructed user
Service work
instructed user
Cleaning work
instructed user
Maintenance work
personnel trained by the
- customer service
Repair work
personnel trained by the
- customer service
Before starting work you must interrupt the compressed air supply to the machine.
➤
Make sure that the machine is free of residual pressure, in both the air and the
material side.
➤
After the completion of work you must in any case check the function of all
protective devices and the correct function of the machine.
2.1.5 Danger caused
by explosion
2.1.6 Danger caused
by disregarding
the explosion
protection
2.2 Operating
personnel
2.2.1 Setup, cleaning,
maintenance
and repair work
Summary of Contents for DUOMIX PU280