Decommissioning
Switch off the equipment if you want to interrupt work.
In case of longer work breaks and / or when changing materials the equipment
needs to be shut down.
1x
1x
2x
Always wear the specified protective clothes.
To avoid malfunctions of the equipment you should take notice of the following:
➤
Never allow the system to run empty.
➤
Do not use any solvents.
For short work breaks you may just switch the equipment to parking position. The
material temperature can be maintained.
1.
Activate parking in the display
➤
Adjust the park modus in the display.
In this respect follow the notes in chapter
Figure 7.1
➤
Reduce the pressure by carefully pulling the trigger of the spray gun.
The pump switches off when the piston of the material pump has reached
bottom position.
➤
Close the material valves on the spray gun.
-
Residual pres-
sure
approx. 50 bar
2.
Switch off the heating (only when required)
0/OFF
Ë
I/ON
Figure 7.2
2.
Shut off the material and compressed air supply on the spray gun, as
described in chap. „11.3.7 End spraying“ of page 11-8
.
The following is required
General notes
7.1 Activating
parking
Notice!
The heaters may remain
activated in parking
position, if necessary. This
maintains the material in
the system at a uniform
temperature.