Translation of the original Operation Manual
7-2
•1307_PU280_SV1018DV1020_BAoDB_en•ski
en
Decommissioning
➤
Switch off the park modus in the display or switch off the equipment complete
-
ly on the control cabinet.
In this respect follow the notes in chapter
3-9.
Figure 7.3
Switch off the equipment completely, if you want to take it out of operation for a
longer time.
1.
Perform the work steps as described in chap.chap. “7.1 Activating park
Switch the heating off too. On versons with material feed container you
must first pump out all material.
2.
Shut off the compressed air supply of the metering pump.
Spray Gun
Feed Pump
Proportioner Pump
6 bar/ 87 psi
6 bar/ 87 psi
0 bar/ 0 psi
Figure 7.4
3.
Reduce the pressure by carefully pulling the trigger of the spray gun.
Close the material valves on the spray gun.
Figure 7.5
4.
Switch off heating
Figure 7.6
7.2 Deactivating
parking
7.3 Take the
system out of
service
Summary of Contents for DUOMIX PU280
Page 68: ......