Translation of the original Operation Manual
10-1
•1307_PU280_SV1018DV1020_BAoDB_en•ski
en
10 Maintenance
According to the accident prevention instructions for “Work with fluid spraying
equipment” BGR 500, chapter 2.36, the unit needs to be regularly inspected and
serviced by an expert (
-Customer Service).
The unit needs to be inspected:
➤
before initial commissioning,
➤
after the modification or repair of parts of the system, which could affect
safety,
➤
after work breaks longer than 6 months,
➤
but at least every 12 months.
For decommissioned units the inspection can be postponed until the next com
-
missioning. The inspection results must be recorded in writing and kept until the
next inspection. The inspection report or a copy thereof must be available at the
place of use of the equipment.
Disassembling the pressurized spraying unit can cause severe injuries to
body and eyes.
➤
Always switch off the equipment before starting maintenance and repair work.
➤
Depressurize the complete system.
➤
Be extremely careful when disassembling material hoses and spray gun.
➤
Before disassembly cover the screw connections on the material hoses with a
cloth to catch possible material spatter.
10.1 Check cycles