3063772_201507
57
32. Commissioning report
Commissioning steps
Test values or confirmation
1.) Gas type
Natural gas E/H
□
Natural gas LL
□
Wobbe index
_____________ kWh/m³
Calorific value, heating _________ kWh/m³
2.) Gas supply pressure checked?
□
3.) Gas leak test carried out?
□
4.) Balanced flue system checked?
□
5.) Water connections checked for leaks?
□
6.) Siphon filled?
□
7.) System flushed?
□
8.) System filled and water treatment carried out in line with
"Design information, water treatment"?
pH value set
Total hardness set
□
________________ pH value
________________ °dH
9.) No chemical additives (inhibitors, antifreeze) added?
□
10.) Boiler and system vented?
□
11.) System pressure 1.5 - 2.5 bar?
□
12.) Gas type and output entered on label?
□
13.) Function test carried out?
□
14.) Flue gas test
Gross flue gas temperature
Ventilation air temperature
Net flue gas temperature
Carbon dioxide content (CO
2
) or oxygen content (O
2
)
Carbon monoxide content (CO)
_____________
t
A
[°C]
_____________
t
A
[°C]
_____________
(t
A
- t
L
) [°C]
_____________
%
_____________
ppm
15.) Casing fitted?
□
16.) System user trained, documentation handed over?
□
17.) Commissioning confirmed?
_____________
□