Setup & Operation
Setup & Operation
15doc041620
2-1
2
SECTION 2 SETUP & OPERATION
2.1. Sawmill Setup
IMPORTANT!
Before starting to use the sawmill, you have to meet
the following conditions:
Set up the sawmill on firm, level ground. Level the machine. Then secure the sawmill to
the ground to prevent moving during operation. A concrete foundation (rated to support
31T/m
2
at each sawmill foot position) and 16mm anchored bolts are recommended.
The sawmill must not be operated indoors without a sawdust extraction system connected
and started.
AC sawmills must not be used outdoors when it is raining or snowing. In such a case, they
must be used and stored under roof or indoors.
The sawmill can be operated in the temperature range of -15
o
C to 40
o
C.
The intensity of light at the operator’s work-place must be at least 300lx.
The operator’s work-place is shown in the figure below.
Have a qualified electrician install the power supply (according to EN 60204 Standard).
The power supply must meet the specifications given in the table below.
!!
Operator’s
Work-Place