3. Installation
3.1. LIFTING AND UNLOADING
The machine can be transported by two means:
- with a forklift truck. To do so, the machine is secured on a
pallet with four hex bolts.
- by several persons. Here, the machine is carried by means of
carrying straps or two battens (A, Fig.1) placed underneath the
thicknesser bed.
CAUTION
Do not carry the machine holding it at the infeed and outfeed
tables, these are not designed to withstand the tensile load by
the machine weight.
3.2 POSITION OF THE MACHINE
CAUTION
It is prohibited to install the machine in explosive environments.
Ensure that the floor area around the machine is level, well
maintained and free from loose material e.g. chips;
1. Remove four mounting bolts from the machine base.
2. Lift machine off the pallet and set down on the floor.
3. Fix the machine to the floor. Fix the machine feet and fix on
ground by means of expansion bolts (not supplied).
3.3 IDENTIFYING SHIPPING BOXES
BEFORE ASSEMBLY
It is advisable that before unpacking to have plenty of paper
towels or cloths available to clean off the rust preservative.
A
FIG. 1
FIG. 2
FIG. 3
-6-