background image

STEP 6

FEMALE

PVC WASHER

STEP 7

MALE

PVC WASHER

3|6

It is recommened to 

lubricate threaded shafts 

to prevent the Nyloc nuts 

from freezing due to friction

(Vaseline or copperslip is 

 recommended).

 

Crank Holder

STEP 6 - ATTACHING THE VERTICAL STRUCTURE WITH GEAR BOX TO THE ROOF STRUCTURE

• 

IDENTIFY AND PROPERLY ALIGN THE PVC WASHERS IN THEIR CORRECT POSITIONS BETWEEN THE VERTICAL STRUCTURE AND ROLLERS

     AS ILLUSTRATED.

• 

ALIGN THE SQUARE SHAFT ON THE CENTER ROLLER WITH THE SQUARE OPENING ON THE GEAR BOX.  INSERT THE SHAFT INTO THE GEAR BOX.  

     IF IT DOES NOT FIT PROPERLY, TURN THE BLACK CRANK HOLDER ON THE GEAR BOX UNTIL THE SQUARE HOLE IS ALIGNED AND INSERT.  

• 

PLACE THE FEMALE PVC SPACER AGAINST THE GEAR BOX ON THE OUTSIDE OF THE CENTER POLE AND ADD THE STAINLESS STEEL WASHER

      AND NYLOC NUT.  

 

• 

INSERT THE THREADED SHAFTS ON THE SIDE ROLLERS INTO EACH OF THE SIDE ARMS AND ADD ALL THE STAINLESS STEEL WASHERS AND 

     REMAINING NYLOC NUTS.

• 

TIGHTEN THE NYLOC NUTS TO THE POINT THEY HOLD FIRM , BUT THE ROLLERS STILL ROTATE FREELY.

  

    

STEP 7 - ATTACH REMAINING VERTICAL STRUCTURE TO THE ROOF STRUCTURE

• 

IDENTIFY AND PROPERLY ALIGN THE PVC WASHERS IN THEIR CORRECT POSITIONS BETWEEN THE VERTICAL STRUCTURE 

     AND ROLLERS AS ILLUSTRATED.

• 

INSERT THE THREADED SHAFTS ON THE SIDE ROLLERS INTO EACH OF THE SIDE ARMS AND ADD ALL THE STAINLESS STEEL 

     WASHERS AND REMAINING NYLOC NUTS.

• 

TIGHTEN THE NYLOC NUTS TO THE POINT THEY HOLD FIRM , BUT THE ROLLERS STILL ROTATE FREELY.

NOTE: THE ROOF STRUCTURE IS A FREE 

SPINNING SYSTEM.  THE NYLOC NUTS 

SECURING BOTH SIDES SHOULD ONLY BE 

TIGHTENED TO THE POINT THE NYLOC NUTS 

HOLD FIRM, AND THE ROLLERS STILL ROTATE 

FREELY.

 

Gear Box

Standard

PVC Washers

Standard PVC Washers

  Distributor: Shadescapes Americas     TEL: 970.527.7070     www.shadescapesamericas.com     info@shadescapesusa.com     © PROTRADE & WOODLINE cc. 2000      

Reviews: