INSTALLING THE LIFTING TOWER
PLACING THE LOAD
O
. nce the tower will be balanced and fixed to the ground, you can proceed to place the load on the incorporate
WINCH OPERATION ( Special Care)
LW 461R / LW 476R LIFTERS
LW 461R / LW 476R LIFTERS
- 9 -
- 10 -
USING & INSTALLATION USER MANUAL
USING & INSTALLATION USER MANUAL
During the tower elevation process, pay attention to the cable rolling.
This cable must the coiled in parallel turns around the winch cylinder NEVER MUST
BE PRODUCED CABLE CROSSES IN DIFFERENT DIRECTIONS.
In this way, that cable can be dangered or got worn, causing, at the end, the break of the cable.
If any spiral is rolled in this way, turn the winch in opposite sense up to release of wrong turn.
Then, proceed to coil again in an appropriated way
Coil direction during
the elevation process
CORRECT MODE
WRONG MODE
The cable must be
coiled in parallel coil
Turned in cross way.
Try to avoid it in order
to keep the cable integrity.
Pin bolt for
leg insertion
In order to insert the legs, use
corresponding pin bolt and
insert the leg to correct position
triggering the bolt To ensure
the set stability.
Rotate the crank of the stabilizer placed on each legs up to the wheels located in the base
do not touch the ground. During this process, control the vial in order to act
each stabilizer up to obtain a perfect balance.
individually over
Vial for level control
support.
Support in stand position for transport. Extract the pin bolts and place it in horizontal position in order to locate
the load.
ATTENTION !!!
For added security during transport, these towers
incorporate a locking system that prevents the movement
of the profiles. This bolt, which is placed in the most external
profile, MUST BE UNBLOCKED BEFORE unfolding the
lifter.
NOTE: REMEMBER TO RELEASE IT BEFORE UNFOLDING THE LIFTER
AND TO BLOCK IT WHEN THE LIFTER WILL BE FOLDED..