background image

The previously assembled 
bearing block and vertical post 
assembly from step 3 are inserted 
into the sigma posts with the short 
vertical posts serving as the front 
and the longer vertical posts as 
the rear legs of the array.

The posts are aligned on site in 
accordance with the tilt angle 
of the rack; a minimum lapped 
joint length of approximately 
12 in. (200 mm) is needed for 
attachment.

The base rails (ST-AK 182-120) are fastened 
to the bearing blocks with 4 T-bolts assemblies 
attached by sliding head of the T-bolts into the two 
slots on the bottom of the base rails (ST-AK 182-
120)on the north-south axis. 

See Figure 5.1

The T-Bolts must be turned 45° clockwise until 
they cannot be turned any further.

A line on the bottom of the T-Bolts shows proper 
alignment. Line must be perpendicular to rail. 
(Torque hex nuts: 10 ft. lbs.) 

See Figure 5.2

Base rail is now securely fastened to the bearing 
block. 

See Figure 5.3

After the frame is complete 
the system must be fixed to the 
sigma post with the supplied 
M10 x 120mm hardware. The 
vertical posts can be moved 
up and down to achieve the 
required tilt angle. When the 
correct angle is achieved a 
cordless drill with a 7/16 bit 

must be used to drill through the existing holes in the sigma post and through 
the aluminum vertical post before the hardware can be installed. Again, the 
vertical post must contact the sigma post for a minimum of 12 in. (200 mm).
(Torque: 10 ft. lbs.)

After the system rails are attached 
to the bearing blocks, the upper 
module rails are attached 
lengthwise. This requires 4 cross 
adapters per intersection point.

Click the cross adapters onto the 
base rails and slide attachment 
lip into channel on base rail. 
Fasten the clamp screws by turning 
clockwise. 

See Figures 6.1 & 

6.2 

(Torque: 10 ft. Lbs)

Module mounting rail is now properly fastened to base rails. Four cross 
adapters are used at each of these connections

To line up several system rails 
with one another, slide the splice 
halfway onto the assembled 
system rail until rivet on splice stops 
forward movement.

Next, slide the other system rail 
onto the splice. Push complete and 
add cross adapter if applicable. 
Splice does not have to occur at a 
cross rail. Splice is now properly 

installed and will allow the rail to perform under thermal expansion and 
contraction. Do not attempt to through-bolt splice. ½” gap or separation 
between rails is required for thermal expansion. 

Portrait Mode Framed PV-Modules

ground-Mount application

Fig. 4.1

Fig. 5.1

Fig. 5.2

Fig. 5.3

Subject to technical changes   

 

Copyright © 2009 HatiCon Solar, LLC   

 

Page 

3

 of 

8

 

 

The previously assembled bearing block and vertical 
post assembly from step 3 are inserted into the sigma 
posts with the short vertical posts serving as the front 
and the longer vertical posts as the rear legs of the 
array.   
 
The posts are aligned on site in accordance with the tilt 
angle of the rack; a minimum lapped joint length of 
approximately 12 in. (200 mm) is needed for 
attachment.  
 
 
 
 
The base rails (ST-AK 182-120) are fastened to the 
bearing  blocks with 4 T-bolts assemblies attached by 
sliding head of the T-bolts into the two slots on the 
bottom of the base rails (ST-AK 182-120)on the north-
south axis.   
See Figure 5.1 
 

 

 
 
 

 

 
 

The T-Bolts must be turned 45° clockwise until they 
cannot be turned any further. 
 

A line on the bottom of the T-Bolts shows proper 
alignment. Line must be perpendicular to rail. 
(Torque hex nuts: 10 ft. lbs.) 

 See Figure 5.2 
 
 
 
 
 
Base rail is now securely fastened to the bearing block. 
See Figure 5.3 

 

 
 
 

 
 

 

4.1 

 

 

 

 

 

5.2 

5.3 

5.1 

   

12 in. minimum 

Subject to technical changes   

 

Copyright © 2009 HatiCon Solar, LLC   

 

Page 

3

 of 

8

 

 

The previously assembled bearing block and vertical 
post assembly from step 3 are inserted into the sigma 
posts with the short vertical posts serving as the front 
and the longer vertical posts as the rear legs of the 
array.   
 
The posts are aligned on site in accordance with the tilt 
angle of the rack; a minimum lapped joint length of 
approximately 12 in. (200 mm) is needed for 
attachment.  
 
 
 
 
The base rails (ST-AK 182-120) are fastened to the 
bearing  blocks with 4 T-bolts assemblies attached by 
sliding head of the T-bolts into the two slots on the 
bottom of the base rails (ST-AK 182-120)on the north-
south axis.   
See Figure 5.1 
 
 
 
 
 
 

 
 

The T-Bolts must be turned 45° clockwise until they 
cannot be turned any further. 
 
A line on the bottom of the T-Bolts shows proper 
alignment. Line must be perpendicular to rail. 
(Torque hex nuts: 10 ft. lbs.) 
 See Figure 5.2 
 
 
 
 
 
Base rail is now securely fastened to the bearing block. 
See Figure 5.3 

 

 
 
 

 
 

 

4.1 

 

 

 

 

 

5.2 

5.3 

5.1 

   

12 in. minimum 

Subject to technical changes   

 

Copyright © 2009 HatiCon Solar, LLC   

 

Page 

3

 of 

8

 

 

The previously assembled bearing block and vertical 
post assembly from step 3 are inserted into the sigma 
posts with the short vertical posts serving as the front 
and the longer vertical posts as the rear legs of the 
array.   
 
The posts are aligned on site in accordance with the tilt 
angle of the rack; a minimum lapped joint length of 
approximately 12 in. (200 mm) is needed for 
attachment.  
 
 
 
 
The base rails (ST-AK 182-120) are fastened to the 
bearing  blocks with 4 T-bolts assemblies attached by 
sliding head of the T-bolts into the two slots on the 
bottom of the base rails (ST-AK 182-120)on the north-
south axis.   
See Figure 5.1 
 
 
 
 
 
 

 
 

The T-Bolts must be turned 45° clockwise until they 
cannot be turned any further. 
 
A line on the bottom of the T-Bolts shows proper 
alignment. Line must be perpendicular to rail. 
(Torque hex nuts: 10 ft. lbs.) 
 See Figure 5.2 
 
 
 
 
 
Base rail is now securely fastened to the bearing block. 
See Figure 5.3 

 

 
 
 

 
 

 

4.1 

 

 

 

 

 

5.2 

5.3 

5.1 

   

12 in. minimum 

Subject to technical changes   

 

Copyright © 2009 HatiCon Solar, LLC   

 

Page 

3

 of 

8

 

 

The previously assembled bearing block and vertical 
post assembly from step 3 are inserted into the sigma 
posts with the short vertical posts serving as the front 
and the longer vertical posts as the rear legs of the 
array.   
 
The posts are aligned on site in accordance with the tilt 
angle of the rack; a minimum lapped joint length of 
approximately 12 in. (200 mm) is needed for 
attachment.  
 
 
 
 
The base rails (ST-AK 182-120) are fastened to the 
bearing  blocks with 4 T-bolts assemblies attached by 
sliding head of the T-bolts into the two slots on the 
bottom of the base rails (ST-AK 182-120)on the north-
south axis.   
See Figure 5.1 
 

 

 
 
 

 

 
 

The T-Bolts must be turned 45° clockwise until they 
cannot be turned any further. 
 

A line on the bottom of the T-Bolts shows proper 
alignment. Line must be perpendicular to rail. 
(Torque hex nuts: 10 ft. lbs.) 

 See Figure 5.2 
 
 
 
 
 
Base rail is now securely fastened to the bearing block. 
See Figure 5.3 

 

 
 
 

 
 

 

4.1 

 

 

 

 

 

5.2 

5.3 

5.1 

   

12 in. minimum 

Subject to technical changes   

 

Copyright © 2009 HatiCon Solar, LLC   

 

Page 

4

 of 

8

 

 

After the frame is complete the system must be fixed to 
the sigma post with the supplied M10 x 120mm 
hardware. The vertical posts can be moved up and 
down to achieve the required tilt angle. When the 
correct angle is achieved a cordless drill with a 7/16 bit 
must be used to drill through the existing holes in the 
sigma post and through the aluminum vertical post 
before the hardware can be installed.  Again, the 
vertical post must contact the sigma post for a 
minimum of 12 in. (200 mm).  
(Torque: 10 ft. lbs.) 
 
 
 
 
After the system rails are attached to the bearing 
blocks,   the upper module rails are attached 
lengthwise. This requires 4 cross adapters per 
intersection point.  
 
Click the cross adapters onto the base rails and slide 
attachment lip into channel on base rail. Fasten the 
clamp screws by turning clockwise. 
See Figures 6.1 & 6.2 
 (Torque: 10 ft. Lbs) 
 
Module mounting rail is now properly fastened to base 

rao 

rails. Four cross adapters are used at each of these  
connections. 
 
 
 
 
 

 

To line up several system rails with one another, slide  
the splice halfway onto the assembled system rail until 

 

rivet on splice stops forward movement 
 
 
 
Next, slide the other system rail onto the splice. Push 
complete and add cross adapter if applicable.  Splice 
does not have to occur at a cross rail. Splice is now 
properly installed and will allow the rail to perform 
under thermal expansion and contraction. Do not 
attempt to through bolt splice. 

½” gap or separation 

between rails is required for thermal expansion. 

 
 
 

 

Click 

   ST-AK 
182/120 

6.1 

6.3 

 

 

7.1 

 

 

6.2 

7.2 

Subject to technical changes   

 

Copyright © 2009 HatiCon Solar, LLC   

 

Page 

4

 of 

8

 

 

After the frame is complete the system must be fixed to 
the sigma post with the supplied M10 x 120mm 
hardware. The vertical posts can be moved up and 
down to achieve the required tilt angle. When the 
correct angle is achieved a cordless drill with a 7/16 bit 
must be used to drill through the existing holes in the 
sigma post and through the aluminum vertical post 
before the hardware can be installed.  Again, the 
vertical post must contact the sigma post for a 
minimum of 12 in. (200 mm).  
(Torque: 10 ft. lbs.) 
 
 
 
 
After the system rails are attached to the bearing 
blocks,   the upper module rails are attached 
lengthwise. This requires 4 cross adapters per 
intersection point.  
 
Click the cross adapters onto the base rails and slide 
attachment lip into channel on base rail. Fasten the 
clamp screws by turning clockwise. 
See Figures 6.1 & 6.2 
 (Torque: 10 ft. Lbs) 
 
Module mounting rail is now properly fastened to base 

rao 

rails. Four cross adapters are used at each of these  
connections. 
 
 
 
 
 

 

To line up several system rails with one another, slide  
the splice halfway onto the assembled system rail until 

 

rivet on splice stops forward movement 
 
 
 
Next, slide the other system rail onto the splice. Push 
complete and add cross adapter if applicable.  Splice 
does not have to occur at a cross rail. Splice is now 
properly installed and will allow the rail to perform 
under thermal expansion and contraction. Do not 
attempt to through bolt splice. 

½” gap or separation 

between rails is required for thermal expansion. 

 
 
 

 

Click 

   ST-AK 
182/120 

6.1 

6.3 

 

 

7.1 

 

 

6.2 

7.2 

Fig. 6.1

Fig. 6.2

Fig. 6.3

Subject to technical changes   

 

Copyright © 2009 HatiCon Solar, LLC   

 

Page 

4

 of 

8

 

 

After the frame is complete the system must be fixed to 
the sigma post with the supplied M10 x 120mm 
hardware. The vertical posts can be moved up and 
down to achieve the required tilt angle. When the 
correct angle is achieved a cordless drill with a 7/16 bit 
must be used to drill through the existing holes in the 
sigma post and through the aluminum vertical post 
before the hardware can be installed.  Again, the 
vertical post must contact the sigma post for a 
minimum of 12 in. (200 mm).  
(Torque: 10 ft. lbs.) 
 
 
 
 
After the system rails are attached to the bearing 
blocks,   the upper module rails are attached 
lengthwise. This requires 4 cross adapters per 
intersection point.  
 
Click the cross adapters onto the base rails and slide 
attachment lip into channel on base rail. Fasten the 
clamp screws by turning clockwise. 
See Figures 6.1 & 6.2 
 (Torque: 10 ft. Lbs) 
 
Module mounting rail is now properly fastened to base 

rao 

rails. Four cross adapters are used at each of these  
connections. 
 
 
 
 
 

 

To line up several system rails with one another, slide  
the splice halfway onto the assembled system rail until 

 

rivet on splice stops forward movement 
 
 
 
Next, slide the other system rail onto the splice. Push 
complete and add cross adapter if applicable.  Splice 
does not have to occur at a cross rail. Splice is now 
properly installed and will allow the rail to perform 
under thermal expansion and contraction. Do not 
attempt to through bolt splice. 

½” gap or separation 

between rails is required for thermal expansion. 

 
 
 

 

Click 

   ST-AK 
182/120 

6.1 

6.3 

 

 

7.1 

 

 

6.2 

7.2 

Fig. 7.1

Fig. 7.2

Assembly Instructions 

13

Solar 

Mounting Sytem

Summary of Contents for Framed PV

Page 1: ...Solar Mounting System Assembly Instructions...

Page 2: ......

Page 3: ...n sliding the rear post vertically until the next adjustment hole is visible through the hole in which the bolt was removed Fasten all triangles at desired tilt angle Framed Modules portrait Framed Mo...

Page 4: ...bject to technical changes Copyright 2009 HatiCon Solar LLC Page Assembly sequence of the flat roof First the angle brackets must be assembled b fastening T Bolt nut and washer Hardware m remain loose...

Page 5: ...of 11 Installing Triangles Triangles can now be mounted to base rails To do this properly space triangles on the base rail per the structural site specific drawings and attach with cross adapters A to...

Page 6: ...6 1 One of these is mounted for each completed row and at least one for every 40 ft The diagonal straps are fastened to the rear triangle struts using T Bolts See Figure 6 2 Torque 6 to 8 ft lbs Insta...

Page 7: ...s Clamps should be attached of the way down from the edge of the module See Figure 9 2 Then slide the module into the thin film end clamp and tighten the T Bolts clockwise Torque 6 to 8 ft lbs Next sl...

Page 8: ...g instructions reflect the state of technology and our experience on how to install our systems on site Due to the fact that each roof has individual characteristics we highly recommend commissioning...

Page 9: ...can be attached using a splice To install simply insert the splice into the end of the rail that will need to be joined until the rivet on the middle of the splice stops the insertion Then slide the o...

Page 10: ...click the mid clamp onto the mounting rail an slide it onto the module Ensure that the mid clam clicks onto both sides of the mounting rail See Figure 4 2 Now slide the next module under the mid clam...

Page 11: ...the horizontal substrate rails for each row of modules using the cross adapters Click the cross adapters onto the base rails and slide attachment lip into channel on base rail Fasten the clamp screws...

Page 12: ...uring installation If a concrete foundation is prepared the sinking of the sigma posts with rebar requires a reinforced foundation A hole must be drilled within 8 inches of the bottom of the sigma pos...

Page 13: ...nges Copyright 2009 HatiCon Solar LLC Page 3 of 8 The previously assembled bearing block and vertical post assembly from step 3 are inserted into the sigma posts with the short vertical posts serving...

Page 14: ...ardware ST AK 120 90 Mounting Rail ST AK 120 90 Splice ST AK 60 37 Mounting Rail ST AK 60 37 Splice ST AK 66 37 Mounting Rail ST AK 66 37 Splice The designs are based on the following codes 2006 Inter...

Page 15: ...side of bearing block must face thin side of vertical post profile to maintain structural Integrity See Figures 3 1 and 3 2 Nut and washer must be fastened on the thick side of the vertical post extru...

Page 16: ...est axis See Figure 5 1 5 2 The T Bolts must be turned 45 clockwise until they cannot be turned any further See Figure 5 2 A line on the bottom of the T bolts shows proper alignment Line must be perpe...

Page 17: ...ils and slide attachment lip into channel of base rail on either side See Figures 7 1 7 2 Fasten the clamp screws by turning clockwise Torque to 6 to 8 ft Lbs ST AK 60 37 7 1 7 2 Fig 8 1 Fig 8 2 Subje...

Page 18: ...f a column of landscape oriented modules See Figure 10 3 Once the module is mounted click the mid clamp onto the module rail and slide the clamp onto the module frame See Figure 10 4 10 4 10 3 Adjusta...

Page 19: ......

Page 20: ...W rth Canada Limited Limit e 6330 Tomken Road Mississauga Ontario Canada L5T 1N2 Tel 905 564 6225 Fax 905 564 3671 www wurthcanada com...

Reviews: