Safety
x
152379 Rev C
Operational Safety Procedures
Never work alone when servicing this equipment. A team of two is required until
the equipment is properly de-energized, locked-out and tagged, and verified de-
energized with a meter.
Thoroughly inspect the equipment prior to energizing. Verify that no tools or
equipment have inadvertently been left behind.
Lockout and Tag
Safety requirements mandate that this equipment not be serviced while energized.
Power sources for the PV100S must be locked-out and tagged prior to servicing.
Each energy source should have a padlock and tag installed on each energy source
prior to servicing.
The PV100S can be energized from both the AC source and the DC source. To
ensure that the inverter is de-energized prior to servicing, lockout and tag the
PV100S using the following procedure.
1. Open, lockout, and tag the incoming power at the utility main circuit breaker.
2. Open, lockout, and tag the AC Disconnect Switch (S1) on AC interface
assembly.
See Figure 1-8 on page 1–12 for the location of the AC Disconnect
Switch.
3. Open, lockout, and tag the DC Disconnect Switch (S2) on DC interface
assembly. See Figure 1-8 on page 1–12 for the location of the DC Disconnect
Switch.
4. Using a confirmed, accurate meter, verify all power to the inverter is de-
energized. A confirmed, accurate meter must be verified on a known voltage
before use. Ensure that all incoming energy sources are de-energized by
checking the following locations.
a)
Inverter Terminals
:
TB4-A, TB4-B, TB4-C
(Phase A, B, C)
See Figure 5-1 on page 5–4.
b)
Utility Terminals
:
Top of S1-2T1, S1-4T2, S1-6T3
See Figure 5-2 on page 5–4.
c)
PV Terminals
:
Bottom of TB3-1, TB3-2, TB3-3
(PV+, PV-, GND)
See Figure 5-3 on page 5–5.
WARNING: Shock Hazard
Review the system schematic for the installation to verify that all available energy sources
are de-energized. DC bus voltage may also be present. Be sure to wait the full 5 minutes to
allow the capacitors to discharge completely.
Summary of Contents for PV100S-208
Page 2: ......
Page 3: ...s PV100S 100 kW Grid Tied Photovoltaic Inverter Operation and Maintenance Manual...
Page 8: ...vi...
Page 14: ...xii...
Page 22: ...xx...
Page 78: ...2 38...
Page 86: ...3 8...
Page 104: ...5 8...
Page 109: ...Appendix A Schematics 152379 Rev C A 5 Figure A 1 Electrical Diagram sample...
Page 116: ...Schematics Appendix A A 12 152379 Rev C This page intentionally left blank...
Page 120: ...Warranty and Return WA 4 152379 Rev C...
Page 123: ......