XCHARGE C6EU DC charging station 

 

Preventive maintenance instructions 

 

XCHARGE Europe GmbH, Borsteler Bogen 27 A, 22453 Hamburg, Germany 

 

http://www.xcharge.com/en/ 

 

 

Maintenance by maintenance partners / XCHARGE 

Category 

 Predefined 

maintenance 

cycles 

Expected 

work duration 

Description 

External monitoring of 

EVSE 

1 year 

2 min. 

Checking the body of EVSE for scratches and damage caused 

by transport or vandalism. 

Checking the display and 

control panel 

1 year 

1 min. 

Check that the display and control panel are not damaged. 

Checking the door  

mechanism 

1 year 

2 min. 

Checking the locking mechanism of the front and rear doors, 

i.e. fixing points, handle and lock. Check that the whole lo-

cking system works well. 

Inspection of internal 

covers 

1 year 

12 min. 

Check the internal protection covers and enclosures of the 

EVSE. Please pay attention to dirt, penetrated water and cor-

rosion.  Please remove dust in the charger (if present). 

Replacing the filter mats 

1 year 

10 min. 

Replace the filter mats if cleaning does not restore the  

function. Otherwise, check the cleanliness. Cleaning must be 

carried out (if necessary) in such a way that the filters are not 

damaged. 

Visual component  

inspection 

1 year 

4 min. 

Check that all components are marked as they were when 

the machine was commissioned and are not in the event of a 

fault. Please check for damage and corrosion. 

Checking the cables 

1 year 

7 min. 

Check that all cables are marked as at commissioning, please 

check for damage and loose connections. The valid safety 

rules must be followed and insulated tools must be used. 