XCHARGE C6EU DC charging station
Preventive maintenance instructions
XCHARGE Europe GmbH, Borsteler Bogen 27 A, 22453 Hamburg, Germany
http://www.xcharge.com/en/
Maintenance by maintenance partners / XCHARGE
Category
Predefined
maintenance
cycles
Expected
work duration
Description
External monitoring of
EVSE
1 year
2 min.
Checking the body of EVSE for scratches and damage caused
by transport or vandalism.
Checking the display and
control panel
1 year
1 min.
Check that the display and control panel are not damaged.
Checking the door
mechanism
1 year
2 min.
Checking the locking mechanism of the front and rear doors,
i.e. fixing points, handle and lock. Check that the whole lo-
cking system works well.
Inspection of internal
covers
1 year
12 min.
Check the internal protection covers and enclosures of the
EVSE. Please pay attention to dirt, penetrated water and cor-
rosion. Please remove dust in the charger (if present).
Replacing the filter mats
1 year
10 min.
Replace the filter mats if cleaning does not restore the
function. Otherwise, check the cleanliness. Cleaning must be
carried out (if necessary) in such a way that the filters are not
damaged.
Visual component
inspection
1 year
4 min.
Check that all components are marked as they were when
the machine was commissioned and are not in the event of a
fault. Please check for damage and corrosion.
Checking the cables
1 year
7 min.
Check that all cables are marked as at commissioning, please
check for damage and loose connections. The valid safety
rules must be followed and insulated tools must be used.