background image

 

© Xena Networks – April 2021 

15

 

 

 

 

 

 

Summary of Contents for ValkyrieBay

Page 1: ...a Networks April 2021 1 Val C12 2400G Chassis Installation Guide HOW TO INSTALL VALKYRIE TEST MODULES Version 5 0 Xena Networks ApS Lottenborgvej 26 2nd floor 2800 KGS Lyngby Denmark www xenanetworks...

Page 2: ...tion Metal Number of Slots 12 Cooling 3 pcs 92 mm Papst 3212JH4 Drive Bay 1 x 2 5 SATA Drive with Hot swap Environmental Operating Temperature 10 to 35 C Storage Temperature 30 to 70 C Humidity 8 to 9...

Page 3: ...ist below connect 12 V power cable 8 Mount the alignment bar by mounting the two finger screws 9 Replace the air flow cover by sliding it till it in place and securing the two finger screws on top 10...

Page 4: ...g the polystyrene foam and anti static bags Recommendations For ports that are not in use keep dust caps mounted Do not cover the front or rear ventilation openings in the chassis Clean the chassis mi...

Page 5: ...he installation steps outlined above are described in detail below Please refer to the relevant section STEP 1 Remove the top cover by unscrewing the two finger screws at the back of the chassis STEP...

Page 6: ...orks April 2021 6 STEP 3 Remove the air flow cover by unscrewing the two finger screws on top and sliding it backwards till it releases STEP 4 Remove the alignment bar by loosening the two finger scre...

Page 7: ...Xena Networks April 2021 7 STEP 5 Choose which slot the module should be mounted in and remove the bracket...

Page 8: ...Networks April 2021 8 STEP 6 Slide the module into place and use the screw to secure it Press the test module firmly but carefully into place do not force it and then fasten again with the screw from...

Page 9: ...Xena Networks April 2021 9 Step 7 If needed see list on page 3 connect 12 V power cable Use delivered 12V cable...

Page 10: ...April 2021 10 Step 8 Mount the alignment bar by mounting the two finger screws The alignment bar fixes the modules in place Please make sure the top of the module goes into the appropriate slot in the...

Page 11: ...ng it forward into place and securing the two finger screws on top STEP 10 Position the restraining bar in place and screw the restraining bar tightly in place If sideways adjustments of the modules a...

Page 12: ...Xena Networks April 2021 12 STEP 11 Replace top lid and fasten it with the two finger screws Do not operate the chassis without top lid...

Page 13: ...Xena Networks April 2021 13...

Page 14: ...Xena Networks April 2021 14...

Page 15: ...Xena Networks April 2021 15...

Page 16: ...t xenanetworks com IMPORTANT ALWAYS REMOVE LONG TEST MODULES BEFORE SHIPPING To minimize the risk of damage please remove long test modules before transportation This includes any test module s that e...

Reviews: