CN1100 Access Point - Installation Guide - G7601 - 3.8
This guide may assist in estimating the time required to complete each xMax CN1100 site installation.
Every installation has its own unique requirements, specifications, and challenges. The provided
timelines are subjective.
Estimated Installation Times
ACTIVITY
TIME
NOTES
Unpack and inventory CN1100 shipment box
10 minutes
Assemble CN1100 equipment
(CN1100, Antennas, GPS antenna, Cables)
15 minutes
Mechanical installation of each CN1100
(varies depending upon building or tower installation)
30-60 minutes Not including climb time
Installation of Cat5 cabling
15-45 minutes Depending on length and difficulty
Provisioning / programming
15 minutes
Installation of switch
15-30 minutes
Installation of Cat5 surge arrestors
15-30 minutes Depending on distance from switch
Installation of ground buss for equipment grounding
15-45 minutes
Depending on availability of
existing grounds
Variables
Building and roof access
Use of existing mounts or installation of new mounts
Tower Related Variables
Tower access
Height of equipment to be installed
Type of Cat5 clamping and securing methods
Tower equipment room access
Power locations and availability
Best case scenario for installation of a single CN1100
140 minutes
Any variables will add to this time