36
CN1100 Access Point - Installation Guide - G7601 - 3.8
20.
Install two ferrite beads on this cable, one within 6 inches of the PoE++ Power Supply, and also one
near the other end of this cable.
21.
Connect the supplied AC Power Cord to the PoE++ Power Supply.
22.
After checking all connections, plug the AC Power Cord into a 110 VAC power source.
Within approximately three minutes, the CN1100 initializes and begins broadcasting beacons.
At this time the Status LED glows
GREEN
. If backhaul is not available, the Status LED glows
RED
.
23.
Test the operation of all transmission components, using a Cat5 tester, or xMax xDrive software.
Refer to the
xDrive Installation and Configuration Guide
for instructions.
24.
Document the installation with site photos of the completed work performed. In multiple CN1100
Access Point device installations, be sure to record the device cable color-code and azimuth for
each sector.