Xtreme Power Conversion Corporation
P90L 6kVA & 10kVA User’s Manual
Page 11
Uninterruptible Power Supply
Rack Installation
1.
Attach mounting ears to the side mounting holes of UPS using the screws provided with the ears facing
forward.
2.
Lift the UPS module and slide it onto the mounting rail kits. Attach the UPS module to the rack with the
screws, nuts and washers (user-provided) through its mounting ears and into the rack rails.
3. See Appendix B: P90L-RAIL Installation Guide for further details.
UPS Electrical Installation
Installation and wiring must be performed in accordance with local and national code/regulations.
1.
Make sure the mains wire and breakers in the building are rated for the correct capacity of UPS.
2.
Switch off the main feed before installation.
3. Turn off all the connected devices before connecting to the UPS.
4.
Prepare wires based on the following table:
Model
Wiring Spec (AWG)
Input
Output
Battery
Ground
P90L-6K
8
8
10
8
P90L-10K
6
6
8
6
Note 1:
P90L-6K input and output cords must be removed prior to proceeding with hardwire installation if required
Note 2:
The wiring for P90L-6K should be able to withstand over 40A current. It is recommended to use 8AWG.
Note 3:
The wiring for P90L-10K should be able to withstand over 63A current. It is recommended to use 6AWG or
Step 1
Step 2
Step 3
UPS and Battery Module
Step 1
Step 2
14 in