11
OPERATION
Plumbing
Power must be turned off at the circuit breaker before performing any wiring. Be sure to follow Local and
NEC electrical codes. To provide safe operation, SPS must be properly grounded and bonded.
Input Power for stand-alone operation:
Wire the SPS to the LOAD SIDE of the filter pump timer. It is very important that the SPS is powered only
when the pump is running.
Refer to the wiring label on SPS as well as the diagram below to determine correct wiring connections. The
SPS is shipped from the factory with the configuration jumpers in a separate bag. Until the jumpers are
installed for the desired voltage, the unit should NOT be turned on.
For Canadian models, the SPS shall be connected to a circuit protected by a class A ground fault interrupter.
Be sure to connect the GROUND wire to the green ground screw terminal located on the INSIDE WALL
of the enclosure.
Summary of Contents for 90151
Page 18: ...PARTS LIST 17 ...