3.2.2.
Positioning, installation of the unit on the wall
-
Select the appropriate anchoring material (not included) for the given wall. To use the unit's hanging
system (keyhole), choose a screw with max.
Ø7 mm
with the maximum head diameter up to 13 mm.
-
Use a spirit level to measure the anchor holes for attaching the unit to the wall. Alternatively, place the
unit on the wall with a spirit level, level it, and mark the mounting holes for anchoring the unit.
-
The wall into which you anchor the unit should always be sufficiently strong and cohesive. If necessary,
contact a specialist in the field - structural engineer.
-
Drill holes in the wall and partially screw in the screws for hanging the unit.
-
Mount the unit onto the prepared anchor bolts.
-
Tighten the anchor bolts adequately to secure the unit against any undesired movement - falling.
3.2.3.
Connection of the condensate drain - siphon
-
The unit must always be fitted with a siphon (included in the delivery) connected to a sewer system.
-
Always check the watering of the siphon and the condensate drainage before starting up for the first time
or after shutting down the unit (the unit has been switched off for a long time).
-
The unit is equipped with two condensation drains:
o
Main drain - must always be plugged, designed to drain condensate from the unit as standard. The
outlet is open as standard.
Fig. 11
Fig. 12