The system was tested at the manufacturer’s factory
(WEDECO) and can be put into operation once it has been
integrated on site. A test of the ambient air sensor must be
carried out by WEDECO personnel or instructed staff before
the system is switched on for the first time.
Observe the initial starting up of the system carefully in order
to be able to detect any potential hazardous situations at an
early stage
Make yourself familiar how to operate the touch panel.
Refer to section Operation
.
7. Switch on the ozone system
7.2.4 Setting the Operating Parameters
The built-in pressure gauge indicates the differential pressure to the barometric air pressure
of the place of installation. If the system is installed at altitudes > 500 m above the sea level,
adjust the operating pressure under consideration of the ambient pressure in order to avoid
loss of performance.
Height
(m above sea
level)
Air pressure
(mbar)
0 1013
500 954
1000 901
1500 848
2000 795
3000 703
4000 616
5000 540