Alyza IQ PO4
Commissioning
73
ba76201d03
05/2020
Is sample present in the overflow vessels?
Does the sample in the overflow vessels meet the quality requirements (see
section 7.2 Application conditions,
159)?
Is the Alyza IQ connected to the IQ S
ENSOR
N
ET
(MIQ/JB + Terminal/Controller, is the Alyza IQ displayed as a sensor on the
IQ S
ENSOR
N
ET
terminal,
see section 3.3.18 Setting up a connection with the IQ S
Was the correct altitude or correct air pressure entered in the IQ S
ENSOR
N
ET
system
(menu
<S>
/
Einstellungen/Settings
/ Systemeinstellungen
/
Standorthöhe/
Luftdruck
, see IQ S
ENSOR
N
ET
system operating manual) ?
If a collecting container for separate disposal of the chemical waste is
installed:
Are the collecting container and return line fastened?
Is regular emptying secured?
3.4.2 Stick the label (national language) onto the locking device of the
MultiPort valve
3.4.3 Carrying out the install wizard
When all requirements for the commissioning are met, start the install wizard to
figure 3-32Stick the label (national language) onto the locking device of the MultiPort valve
Before opening: Drain the system!
ES: Antes de abrir: vaciar el sistema!
¡