61U5H11
7-36
9
8
7
6
5
4
3
2
1
PTT unit
8.
Reverse the PTT motor leads between
the battery terminals to fully extend the
trim and tilt rams, and then measure the
hydraulic pressure.
9.
Replace the up relief fitting with the down
relief fitting
5
.
NOTE:
Quickly install the special service tools before
any fluid flows out of the hole.
10. Remove the reservoir cap, and then
check the fluid level.
NOTE:
If the fluid is at the correct level, the fluid
should overflow out of the filler hole when the
reservoir cap is removed.
11. If necessary, add sufficient fluid of the
recommended type until it overflows out
of the filler hole.
12. Install the reservoir cap, and then tighten
it to the specified torque.
Lg
Sb
6G470270
Rams
PTT motor lead
Battery
terminal
Up
Sky blue (Sb)
+
Light green (Lg)
-
Hydraulic pressure (up):
10–12 MPa (100–120 kgf/cm
2
)
Down relief fitting
5
: 90890-06774
Hydraulic pressure gauge:
90890-06776
5
6G470280
6G470240
Reservoir cap:
7 N·m (0.7 kgf·m, 5.2 ft·lb)
61U5H11_07_1 06.2.13 1:24 PM Page 39
Summary of Contents for E115A
Page 1: ...115B SERVICE MANUAL 61U 28197 5H 11 140B E115A E115A 115B 140B ...
Page 4: ......
Page 79: ...61U5H11 4 18 9 8 7 6 5 4 3 2 1 MEMO ...
Page 136: ...POWR 5 55 61U5H11 Power unit MEMO ...
Page 159: ...61U5H11 6 22 9 8 7 6 5 4 3 2 1 Shimming Shimming 6G46090E T3 M3 M4 M1 M2 T1 T2 F R P ...
Page 255: ......