CL600 Operator's Manual
18.Start and run the engine at idle speed.
• Carefully operate the implement control lever (A)
to curl the bucket until the mast assembly is
separated from the loader mount. See the picture
below.
(A) Implement control lever
19.Continue curling the bucket until the entire lower
portion of the bucket rests on the ground.
20.Shut off the engine.
21.Slowly move the implement control lever in all
directions to release the hydraulic pressure.
22.Disconnect the four hoses from the implement
control valves through the hydraulic quick
couplers (A).
23.Place the hoses above the right section of the
boom.
(A) Hydraulic quick couplers
1. Store the loader in a clean, dry location preferably
indoors. Make sure that the loader is properly and
securely supported.
2. Protect the hydraulic quick couplers from dust by
attaching the protective plugs and caps.
3. Inspect all hydraulic hoses, connections and other
parts. As necessary, repair or replace any worn
out, damaged or missing parts.
4. Follow the procedure in "Lubricate" on page 5-1.
Lubricate the loader.
5. In order to prevent rust during storage, apply a
coat of grease to all exposed cylinder rods and
mounting pins. Repaint or replace all worn out
and scratched parts.
(A)
P1110461
(A)
P1110438
2. Store the Loader
P1110474
Summary of Contents for CL Series
Page 46: ...NOTE...