28 | RMB/ENERGIE GmbH
assembly
Operation manual CHP 5.0 - 30.0 | Status 01.2020
5.4.6 Stopping the test run
A
Stop the test run via the operating display.
“RMB/Control” operating manual.
A
Switch off the master switch.
5.4.7 Closing the generation unit
A
Close the generation unit.
The test run has been successful if the following
conditions have been met:
B
The cooling system has been bled.
B
All lines are leak-tight.
B
The control mechanism does not display any error
messages.
B
The system has run for a minimum of 15 minutes.
If the test run has not been successful:
A
Check the assembly steps again up until the
connection inspection.
D
“5.3 Assembly steps” (page 18).
A
Carry out another test run.
D
If the test run has still not been successful:
A
Contact the manufacturer.
After the test run has been successfully completed,
commissioning must be requested from a specialist
partner.
Commissioning request.
Download forms:
Ј
www.rmbenergie.com
A
Arrange a time and date for the commissioning.