5.15 Method 1: Copy One Subtask Job and Create Other Two Jobs
5-33
Executing Conversion
Operation
Explanation
1
Display the PARALLEL SHIFT
JOB window.
2
Select “EXECUTE.”
The confirmation dialog box appears when the converted job is
not specified. Select “YES” then the conversion is executed. The
JOB CONTENT window appears when the conversion is com-
pleted.
R1:X
Y
Z
200.000
0.000
0.000
Overwrite?
YES
NO
PARALLEL SHIFT JOB
SOURCE JOB
STEP SECTION
DESTINATION JOB
COORDINATES
BASE POINT
<SHIFT VALUE>
EDIT
DISPLAY
UTILITY
DATA
Short Cut
Main Menu
CANCEL
EXECUTE
If an alarm occurs during conversion, conversion is
suspended.
SUPPLE-
MENT
0000
0001
0002
0003
0004
0005
MOVJ VJ=100.0
At step outside the
P-point maximum
envelope, "/OV"is
displayed after the
move instruction.
Step exceeding operation range is made
JOB CONTENT: MASTER
JOB NAME: TEST
CONTROL GROUP: R1
STEP NO: 000
TOOL: 00
NOP
’TEST JOB
JUMP JOB:JOB-01
MOVJ VJ=50.00
MOVJ /0V VJ=50.00
MOVJ VJ=50.00
EDIT
DISPLAY
UTILITY
JOB
Short Cut
Main Menu
142/210