3
TRANSPORTATION, HANDLING
AND STORAGE
YCAA series chillers are supplied fully assembled, (with
the exception of the anti-vibration mounts supplied with
the unit) which are installed on site.
R22 units are pre-charged with refrigerant and oil in the
correct quantity required for operation. R407C units are
pre-charged with liquid refrigerant only and oil in the
correct quantity required for operation.
The low pressure side of the refrigerant circuit
on R407C units must be charged using the
service valve on the thermal expansion valve
before the unit is operated.
3.1
Inspection
Immediately upon receiving the unit, it should be
inspected for possible damage which may have
occurred during transit as goods are shipped ex-works
at purchaser's risk. In addition, ensure that all ordered
components have been received.
If any damage is evident, it should be noted on the
carrier's freight bill and a claim entered in accordance
with the advice note instructions. If the damage is other
than superficial, immediately advise your local York
representative.
York accepts no responsibility for shipping
damage, even in cases where the factory has
arranged for shipping.
3.2
Handling
YCAA series chillers are designed to be lifted using
lifting lugs and cables. A spreader bar or frame should
be used with the cables, to avoid crushing the unit.
Before moving the unit ensure that the installation site is
suitable to receive the unit and to support its weight and
mechanical impact.
During handling, avoid touching sharp parts (for
example coil fins).
Never move the unit on rollers or lift the unit
using a fork lift truck.
Proceed as follows to lift and move the unit:
n
Insert and secure the lifting lugs through the
marked holes in the base frame.
n
Attach the cables to the lifting lugs.
n
Insert a spreader bar or frame between the cables,
vertical to the unit's centre of gravity.
n
Attach the crane hook at the unit's centre of gravity.
n
Cable length shall be such that they do not form an
angle of less than 45 degrees to the horizontal
when under tension.
(09/03)
035B09012-100 Rev. 4
3
-
1
Summary of Contents for YCAA B 120
Page 2: ......
Page 16: ...This Page Left Intentionally Blank 09 03 2 6 035B09012 100 Rev 4 ...
Page 28: ...This Page Left Intentionally Blank 09 03 4 10 035B09012 100 Rev 4 ...
Page 36: ...Page Left Intentionally Blank 09 03 6 6 035B09012 100 Rev 4 ...
Page 40: ...Page Left Intentionally Blank 09 03 7 4 035B09012 100 Rev 4 ...
Page 68: ...Notes 09 03 11 2 035B09012 100 Rev 4 ...
Page 69: ...Notes 09 03 035B09012 100 Rev 4 11 3 ...