background image

5120416-XIM-C-0216

Johnson Controls Unitary Products

7

Location

Use the following guidelines to select a suitable location for 
these units:
1.

Unit is designed for 

outdoor installation only

.

2.

Condenser coils must have an unlimited supply of air. 
Where a choice of location is possible, position the unit on 
either north or east side of building.

3.

Suitable for mounting on roof curb.

4.

For ground level installation, use a level concrete slab with 
a minimum thickness of 4 inches. The length and width 
should be at least 6 inches greater than the unit base rails. 
Do not tie slab to the building foundation.

5.

Roof structures must be able to support the weight of the 
unit and its options/accessories. Unit must be installed on a 
solid, level roof curb or appropriate angle iron frame.

6.

Maintain level tolerance to 1/2” across the entire width and 
length of unit.

Clearances

All units require particular clearances for proper operation and 
service. Installer must make provisions for adequate 
combustion and ventilation air in accordance with section 5.3 of 
Air for Combustion and Ventilation of the National Fuel Gas 
Code, ANSI Z223.1 – Latest Edition (in U.S.A.), or Sections 7.2, 
7.3, or 7.4 of Gas Installation Codes, CSA-B149.1 (in Canada) - 
Latest Edition, and/or applicable provisions of the local building 
codes. Refer to Table 4 for clearances required for combustible 
construction, servicing, and proper unit operation.

Rigging And Handling

Exercise care when moving the unit. Do not remove any 
packaging until the unit is near the place of installation. Rig the 
unit by attaching chain or cable slings to the lifting holes 
provided in the base rails. Spreader bars, whose length 
exceeds the largest dimension across the unit, 

MUST

 be used 

across the top of the unit.

Units may be moved or lifted with a forklift, from the side only, 
providing an accessory skid is used.

LENGTH OF FORKS MUST BE A MINIMUM OF 90 INCHES 
(2286MM).

Excessive exposure of this furnace to contaminated 
combustion air may result in equipment damage or 
personal injury. Typical contaminates include: 
permanent wave solution, chlorinated waxes and 
cleaners, chlorine based swimming pool chemicals, 
water softening chemicals, carbon tetrachloride, 
Halogen type refrigerants, cleaning solvents (e.g. 
perchloroethylene), printing inks, paint removers, 
varnishes, hydrochloric acid, cements and glues, anti-
static fabric softeners for clothes dryers, masonry acid 
washing materials.

Do not permit overhanging structures or shrubs to 
obstruct condenser air discharge outlet, combustion air 
inlet or vent outlets.

If a unit is to be installed on a roof curb other than a 
York

®

 roof curb, gasketing must be applied to all 

surfaces that come in contact with the unit underside.

Before lifting, make sure the unit weight is distributed 
equally on the rigging cables so it will lift evenly.

All panels must be secured in place when the unit is 
lifted.
The condenser coils should be protected from rigging 
cable damage with plywood or other suitable material.

Summary of Contents for DC180

Page 1: ...g 43 Start Up Gas Heat 44 Checking Gas Heat Input 44 Simplicity SE Smart Equipment Firmware Version 3 Basic Unit Control Board Navigation Examples 46 Start Up Service Data Instruction 54 LIST OF TABLE...

Page 2: ...hout economizer or motorized damper option only at the point of installation These gas fired heaters have aluminized steel or optional stainless steel tubular heat exchangers with spark ignition with...

Page 3: ...LP with kit If the information in this manual is not followed exactly a fire or explosion may result causing property damage personal injury or loss of life Do not store or use gasoline or other flamm...

Page 4: ...t 3 Smoke Detector S A 4 Smoke Detector R A 5 Pwr d Conv Outlet Options SS Drain Pan Configuration Options not required for all units These four digits will not be assigned until a quote is requested...

Page 5: ...n this document After installation gas fired units must be adjusted to obtain a temperature rise within the range specified on the unit rating plate If components are to be added to a unit to meet loc...

Page 6: ...CIENCY COMPRESSORS COPPER TUBE ALUMINUM FIN CONDENSER COILS ELECTRICAL DISCONNECT MOUNTING LOCATION Field installed KNOCKOUT FOR SIDE CONTROL WIRING ENTRY KNOCKOUT FOR SIDE POWER WIRING ENTRY SIDE KNO...

Page 7: ...r unit operation Rigging And Handling Exercise care when moving the unit Do not remove any packaging until the unit is near the place of installation Rig the unit by attaching chain or cable slings to...

Page 8: ...A B C D 180 Gas 2300 539 563 612 586 240 Gas 2500 538 563 715 684 300 Gas 3130 615 671 962 882 180 Elec 2100 492 514 558 536 240 Elec 2300 295 517 658 630 300 Elec 2890 487 619 646 508 Unit Size Total...

Page 9: ...84 300 Gas 1420 279 304 436 882 180 Elec 953 223 233 253 536 240 Elec 1043 134 235 299 630 300 Elec 1310 221 281 293 508 Unit Size Total Shipping Weight 6 Point Loads kg A B C D E F 180 Gas 1043 159 1...

Page 10: ...iliary DOT PLUG For pressure Drop Reading FRONT VIEW CONTROL BOX ACCESS 21 5 9 3 4 11 1 2 2 3 4 21 1 2 33 35 5 7 8 46 5 8 7 1 8 6 3 8 VENT AIR OUTLET HOODS COMBUSTION AIR INLET HOOD GAS HEAT ACCESS C...

Page 11: ...wer exhaust option The covering consists of a heavy black paper composition 3 Replace the side supply and return air compartment panels For side duct applications 1 Replace the side panels on the supp...

Page 12: ...n Distance mm in Direction Distance mm in Top1 1 Units must be installed outdoors Over hanging structure or shrubs should not obscure condenser air discharge outlet 1829 72 With 914 36 Maximum Horizon...

Page 13: ...h the dimensions of the duct connections on the unit Refer to Figure 5 for bottom air duct openings Refer to Figure 6 for side air duct openings NOTE It is recommended that in Canada the outlet duct b...

Page 14: ...y on the return air ductwork as close to the unit as possible Cut an opening 16 inches high by 18 inches wide in the ductwork to accommodate the damper Using the holes in the hood flanges as a templat...

Page 15: ...d the same minimum gauge as the replaced wire A disconnect must be utilized for these units Factory installed disconnects are available If installing a disconnect field supplied or York International...

Page 16: ...ed insulated wires should be used to connect the thermostat to the unit Refer to Table 5 for control wire sizing and maximum length Space Sensor The space sensor if used should be located on an inside...

Page 17: ...ge ot required on single stage he g units Jumper is required if there is no Smoke Detector circuit Jumper is required for any co of R RC or RH 5 5 OCC is an output from the thermostat to indicate the...

Page 18: ...E 44 4 50 E18 13 5 1 18 8 44 4 50 E36 26 9 2 37 4 55 2 60 E54 40 4 2 56 2 78 6 80 E72 53 8 2 74 8 83 2 90 240 20 380 3 50 20 7 130 29 2 1 8 2 0 NONE 59 70 E18 11 3 1 17 2 59 70 E36 22 6 2 34 3 59 70 E...

Page 19: ...2 or 4 In 12 304 X 609 X 51 or 102 mm QUANTITY PER UNIT 16 X 20 X 2 or 4 In 4 406 X 508 X 51 or 102 mm QUANTITY PER UNIT 16 X 25 X 2 or 4 In 4 406 X 508 X 51 or 102 mm QUANTITY PER UNIT 18 X 24 X 2 or...

Page 20: ...ction External Shut Off NOTE Maximum capacity of pipe in cubic feet of gas per hour based upon a pressure drop of 0 3 inch W C and 0 6 specific gravity gas Gas Connection The gas supply line can be ro...

Page 21: ...ors and between the second stage regulator and the appliance Pipe size required will depend on the length of the pipe run and the total load of all appliances Complete information regarding tank sizin...

Page 22: ...the control sensors are factory mounted as part of the Factory installed economizer option Power Exhaust Barometric Relief Damper and Rain Hood The instructions for the power exhaust barometric relie...

Page 23: ...ing with a demand from the zone return sensor for the first stage of cooling the dampers modulate to control the supply air temperature to the Economizer Setpoint 1 F If the economizer output is at 10...

Page 24: ...rmistor MAT parameter reports input status F C 3 65 VDC reading MAT to COM with open circuit Read only use in current control revision IN1 MAT LEDs at left on upper edge of economizer board POWER POWE...

Page 25: ...g power exhaust actuator and economizer actuator Connects through circuit trace to 24V IN pin HOT ECON 2 10 VDC output for the Economizer actuator Econ parameter reports output status 0 100 Used to po...

Page 26: ...negative for the indoor air quality sensor Connects through circuit trace to 24V IN pin COM R 24V 24 VAC hot supplied for the outdoor air quality sensor Connects through circuit trace to 24V IN pin H...

Page 27: ...edge of economizer board IN9 PURGE 24 VAC hot input from the PURGE dry contact Purge parameter reports input status False with 0 VAC input True with 24 VAC input When Purge status is True heating and...

Page 28: ...lection force is as follows Tension new belts at the max deflection force recommended for the belt section Check the belt tension at least two times during the first 24 hours of operation Any retensio...

Page 29: ...product at altitude Example 1 What are the corrected CFM static pressure and BHP at an elevation of 5 000 ft if the blower performance data is 6 000 CFM 1 5 IWC and 4 0 BHP Solution At an elevation o...

Page 30: ...ution As in the example above no temperature information is given so 70 F is assumed The 1 5 static pressure given is at an elevation of 5 000 ft The first step is to convert this static pressure to e...

Page 31: ...kW Input kW ESP Pa Output kW Input kW ESP Pa Output kW Input kW HIGH STATIC DRIVE m3 s 1030 6 0 357 2 4 2 8 316 2 8 3 4 253 3 3 3 9 183 3 7 4 5 97 4 2 5 0 1070 5 0 405 2 5 3 0 362 3 0 3 6 298 3 5 4 2...

Page 32: ...nput kW ESP iwg Output bhp Input kW ESP iwg Output bhp Input kW HIGH STATIC DRIVE CFM 895 6 0 1 3 4 7 4 0 1 1 5 0 4 3 0 8 5 6 4 8 0 6 6 1 5 2 0 3 6 8 5 8 930 5 0 1 5 5 0 4 3 1 3 5 3 4 5 1 0 6 0 5 1 0...

Page 33: ...kW ESP iwg Output bhp Input kW ESP iwg Output bhp Input kW HIGH STATIC DRIVE CFM 1030 6 0 1 5 3 1 2 7 1 3 3 6 3 2 1 0 4 3 3 8 0 8 4 9 4 4 0 5 5 6 5 0 1070 5 0 1 7 3 3 2 9 1 4 3 8 3 4 1 2 4 5 4 1 1 0 5...

Page 34: ...ESP iwg Output bhp Input kW ESP iwg Output bhp Input kW HIGH STATIC DRIVE CFM 895 6 0 1 5 3 7 3 2 1 0 4 7 4 0 0 5 5 7 4 9 0 1 6 3 5 4 925 5 0 1 6 3 9 3 4 1 2 4 9 4 2 0 6 6 0 5 1 0 3 6 7 5 7 955 4 0 1...

Page 35: ...750 CFM 10000 CFM ESP iwg OUTPUT bhp INPUT kW ESP iwg OUTPUT bhp INPUT kW ESP iwg OUTPUT bhp INPUT kW 945 6 0 1 0 5 6 4 6 0 3 7 0 5 7 975 5 0 1 2 5 9 4 9 0 5 7 3 6 0 1005 4 0 1 4 6 2 5 1 0 7 7 7 6 3 1...

Page 36: ...ure 22 After readings have been obtained remove the tubes and reinstall the two 5 16 dot plugs that were removed in Step 1 Table 14 Blower Motor And Drive Data MODEL SIZE DRIVE1 1 All 50 Hz DM180 300...

Page 37: ...f the blower speed and belt tension are REQUIRED Tighten blower pulley and motor sheave set screws after these adjustments Re checking set screws after 10 12 hours run time is recommended Table 16 Sta...

Page 38: ...d Compressor 2 is energized provided it has not been locked out and condenser fan motor 1 and condenser fan motor 2 remain energized If the ambient temperature is above 60 F To be available a compress...

Page 39: ...pressor is idle stop the condenser fans If the LPS is still open after the ASCD the compressor will not be energized for 30 seconds The second and third times that the UCB sees an open LPS will count...

Page 40: ...UST use a two stage thermostat a Upon a call for heat by the thermostat the heater contactor M6 will be energized After completing the specified fan on delay for heating the UCB will energize the blow...

Page 41: ...energized The RW2 1 contact is closed energizing the second stage ignition module IC2 IC2 will immediately start the second stage igniter sparking and will open the redundant valve located inside the...

Page 42: ...9 It resets automatically The limit switch operates when a high temperature condition caused by inadequate supply air flow occurs thus shutting down the heater and energizing the blower Auxiliary Limi...

Page 43: ...ce Refer to Table 20 for the required gas heat anticipator setting Start Up Cooling Prestart Check List After installation has been completed 1 Check the electrical supply voltage being supplied Be su...

Page 44: ...time needed for one revolution of the hand on the smallest dial on the meter A typical gas meter usually has a 1 2 or a 1 cubic foot test dial 3 Using the number of seconds for each revolution and th...

Page 45: ...Figure 27 Proper Pilot Flame Adjustment Pilot Checkout The pilot flame should envelope the end of the flame sensor To adjust pilot flame 1 remove pilot adjustment cover screw 2 increase or decrease th...

Page 46: ...is on the top Status line hit the ENTER button This action steps the LCD display into the status mode Hit ENTER to view the status menu Press Enter Step 2 7KH UVW LWHP XQGHU WKH status menu is DVent M...

Page 47: ...ER CANCEL JOY C PWR 7 7 77 Clg Engaged LeadLag Engaged Press Enter Joy Stick Down 2 Step 6 By toggling down twice the screen reaches the ClgOcc SP screen or Cooling Occupied Set Point ENTER CANCEL JOY...

Page 48: ...microprocessor connects through circuit trace to the SD 24 terminal SD 24 24 VAC hot out for factory accessory smoke detector condensate overflow and or user shutdown relay switching in series Connec...

Page 49: ...Lit indicates 24 VAC is present at C and 24V terminals FAULT Red hard lockout networking error and firmware error indicator 1 2 second on off flashing indicates one or more alarm is currently active 1...

Page 50: ...C reading EC2 to EC2 with open circuit Used in suction line temperature safety Pinned connections on right edge of UCB RAH Return Air Humidity input from 0 10 VDC 0 100 RH sensor Input required for re...

Page 51: ...tput for indoor blower contactor coil indoor blower VFD enable relay coil Output with heat cool operation G input or schedule demand C1 24 VAC hot output for compressor 1 If demand is present and perm...

Page 52: ...nter of the board Positive of the 15 VDC reading to C circuit for powering an optional netstat and or Multi Touch gateway C Common for SA BUS power and communication circuits Also incorporated in the...

Page 53: ...C Field Connected BUS BACnet MSTP communication circuit Earth ground reference of the cable to prevent interference on the FC bus BACnet MSTP communication circuit Item Selector in red housing at left...

Page 54: ...rtion of our standard warranty policy which states that Johnson Controls UPG will cover parts and labor on new equipment start up failures that are caused by a defect in factory workmanship or materia...

Page 55: ...ll open position and the frequency drive is operating at 60 HZ Do not proceed with the equipment start up without the design CFM information Design Supply Air CFM __________________________ Design Ret...

Page 56: ...and control complete Air Moving Inspection Completed See Notes Alignment of drive components Belt tension adjusted properly Blower pulleys tight on shaft bearing set screws tight wheel tight to shaft...

Page 57: ...to increase of decrease the airflow to meet the design conditions If the motor pulley size was changed measure the outside diameters of the motor and blower pulleys and record those diameters here Bl...

Page 58: ...Return Air Temperature ________________ F db ________________ F wb ________________ RH Mixed Air Temperature ________________ F db ________________ F wb ________________ RH Supply Air Temperature ____...

Page 59: ...__________________________________________________________________ _______________________________________________________________________________________________________ _____________________________...