JOHNSON CONTROLS
40
FORM 150.66-NM3
ISSUE DATE: 09/25/2020
SECTION 5 - COMMISSIONING
Supply Voltage
Verify that the site voltage supply corresponds to the
unit requirement and is within the limits given in
PREPARATION – POWER ON
Perform the commissioning using the
detailed checks outlined in the EQUIP
-
MENT STARTUP CHECK SHEET
as the commissioning procedure is
carried out.
Apply power to the chiller. Turn ON the option panel
circuit breaker if supplied.
The machine is now live!
Switch Settings
Ensure the chiller OFF/ON UNIT switch at the bottom
of the keypad is OFF. Place the optional circuit breaker
handle on the panel door to ON. The customer’s dis-
connection devices can now be set to ON.
Verify the control panel display is illuminated. En-
sure that the system switches under the SYSTEM
SWITCHES key are in the OFF position.
Compressor Heaters
Verify the compressor heaters are energized. If the am-
bient temperature is above 96°F (36°C) the compressor
heaters must be on for at least 8 hours before start-up
to ensure all refrigerant liquid is driven out of the com-
pressor and the oil. If the ambient temperature is below
86°F (30°C), allow 24 hours.
Water System
Verify the chilled liquid system has been installed cor-
rectly, and has been commissioned with the correct
direction of water flow through the cooler. The inlet
should be at the refrigerant piping connection end of
the cooler. Purge air from the top of the cooler using
the plugged air vent mounted on the top of the cooler
body.
Flow rates and pressure drops must be within the limits
given in the Technical Data Section. Operation outside
of these limits is undesirable and could cause damage
.
If mains power must be switched OFF for extended
maintenance or an extended shutdown period, the com-
pressor suction, discharge and economizer service stop
valves should be closed (clockwise). If there is a pos-
sibility of liquid freezing due to low ambient tempera-
tures, the coolers should be drained or power should be
applied to the chiller. This will allow the cooler heater
to protect the cooler from freezing down to –20°F. Be-
fore placing the unit back in service, valves should be
opened and power must be switched on (if power is
removed for more than 8 hours) for at least 8 hours (24
hours if ambient temperature is below 86°F [30°C])
before the unit is restarted.
Flow Switch
Verify a chilled water flow switch is correctly fitted in
the customer’s piping on the cooler outlet, and wired
into the control panel correctly using shielded cable.
There should be a straight run of at least 5 pipe di-
ameters on either side of the flow switch. The flow
switch should be connected to terminals 13 and 14 in
the panel.
Temperature Sensor(s)
Ensure that the leaving liquid temperature sensor is
coated with heat conductive compound (Part No. 013-
00890-000) and is inserted to the bottom of the water
outlet sensor well in the cooler. This sensor also pro-
vides some freeze protection and must always be fully
inserted in the water outlet sensor well.
Summary of Contents for YCAL Series
Page 4: ...JOHNSON CONTROLS 4 FORM 150 66 NM3 ISSUE DATE 09 25 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 16: ...JOHNSON CONTROLS 16 FORM 150 66 NM3 ISSUE DATE 09 25 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 130: ...JOHNSON CONTROLS 130 FORM 150 66 NM3 ISSUE DATE 09 25 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 144: ...JOHNSON CONTROLS 144 FORM 150 66 NM3 ISSUE DATE 09 25 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 173: ...FORM 150 66 NM3 ISSUE DATE 09 25 2020 173 JOHNSON CONTROLS 10 NOTES...