1. Floor or steel frame should be level and smooth.
2. For pad installations, isolators do not normally
require bolting. If necessary, anchor isolators to
floor through bolt holes in the base plate.
Isolators must be bolted to the sub
structure and the equipment must be
bolted to the isolators when outdoor
equipment is exposed to wind forces.
3. Lubricate the threads of adjusting bolt. Loosen the
hold down bolts to allow for isolator adjustment.
4. Block the equipment 10 mm (1/4 in.) higher than
the specified free height of the isolator. To use the
isolator as blocking for the equipment, insert a 10
mm (1/4 in.) shim between the upper load plate
and vertical uprights. Lower the equipment on the
blocking or shimmed isolators.
5. Complete piping and fill equipment with water,
refrigerant, etc.
6. Turn leveling bolt of first isolator four full revolu
-
tions and proceed to each mount in turn.
7. Continue turning leveling bolts until the equipment
is fully supported by all mountings and the equip-
ment is raised free of the spacer blocks or shims.
Remove the blocks or shims.
8. Turn the leveling bolt of all mountings in either
direction in order to level the installation.
9. Tighten the nuts on hold down bolts to permit
a clearance of 2 mm (1/8 in.) between resilient
washer and underside of channel cap plate.
10. Installation is now complete.
Summary of Contents for YCAL0012EC
Page 12: ...JOHNSON CONTROLS 12 FORM 150 66 NM2 ISSUE DATE 09 25 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 16: ...JOHNSON CONTROLS 16 FORM 150 66 NM2 ISSUE DATE 09 25 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 98: ...JOHNSON CONTROLS 98 FORM 150 66 NM2 ISSUE DATE 09 25 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 142: ...JOHNSON CONTROLS 142 FORM 150 66 NM2 ISSUE DATE 09 25 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 165: ...FORM 150 66 NM2 ISSUE DATE 09 25 2020 165 JOHNSON CONTROLS NOTES...