JOHNSON CONTROLS
40
FORM 150.66-NM2
ISSUE DATE: 09/25/2020
SECTION 5 - COMMISSIONING
Supply Voltage
Verify that the site voltage supply corresponds to the
unit requirement and is within the limits given in the
Technical Data Section.
PREPARATION – POWER ON
Perform the commissioning using
the detailed checks outlined in the
Equipment Startup Checklist as the
commissioning procedure is carried
out.
Apply power to the chiller. Turn ON the option panel
circuit breaker if supplied.
The machine is now live!
Switch Settings
Ensure the chiller OFF/ON UNIT switch at the
bottom of the keypad is OFF. Place the optional
circuit breaker handle on the panel door to ON. The
customer’s disconnection devices can now be set to
ON.
Verify the control panel display is illuminated.
Ensure
the system switches under the SYSTEM SWITCHES
Key are in the OFF position.
Compressor Heaters
Verify the compressor heaters are energized. If
the ambient temperature is above 96°F (36°C) the
compressor heaters must be on for at least 8 hours
before start-up to ensure all refrigerant liquid is driven
out of the compressor and the oil. If the ambient
temperature is below 86°F (30°C), allow 24 hours.
Water System
Verify the chilled liquid system has been installed
correctly, and has been commissioned with the correct
direction of water flow through the cooler. The inlet
should be at the refrigerant piping connection end of
the cooler. Purge air from the top of the cooler using
the plugged air vent mounted on the top of the cooler
body.
Flow rates and pressure drops must be within the
limits given in the Technical Data Section. Operation
outside of these limits is undesirable and could cause
damage.
If mains power must be switched OFF for extended
maintenance or an extended shutdown period, the
compressor suction, discharge and economizer service
stop valves should be closed (clockwise). If there is
a possibility of liquid freezing due to low ambient
temperatures, the coolers should be drained or power
should be applied to the chiller. This will allow the
cooler heater to protect the cooler from freezing down
to –20°F. Before placing the unit back in service,
valves should be opened and power must be switched
on (if power is removed for more than 8 hours) for
at least 8 hours (24 hours if ambient temperature is
below 86°F [30°C]) before the unit is restarted.
Flow Switch
Verify a chilled water flow switch is correctly fitted in
the customer’s piping on the cooler outlet, and wired
into the control panel correctly using shielded cable.
There should be a straight run of at least 5 pipe
diameters on either side of the flow switch. The flow
switch should be connected to terminals 2 and 13 in
the panel.
Temperature Sensor(s)
Ensure the leaving liquid temperature sensor is coated
with heat conductive compound (Part No. 013-00890-
000) and is inserted to the bottom of the water outlet
sensor well in the cooler. This sensor also provides
some freeze protection and must always be fully
inserted in the water outlet sensor well.
Summary of Contents for YCAL0012EC
Page 12: ...JOHNSON CONTROLS 12 FORM 150 66 NM2 ISSUE DATE 09 25 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 16: ...JOHNSON CONTROLS 16 FORM 150 66 NM2 ISSUE DATE 09 25 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 98: ...JOHNSON CONTROLS 98 FORM 150 66 NM2 ISSUE DATE 09 25 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 142: ...JOHNSON CONTROLS 142 FORM 150 66 NM2 ISSUE DATE 09 25 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 165: ...FORM 150 66 NM2 ISSUE DATE 09 25 2020 165 JOHNSON CONTROLS NOTES...